Cranwell Traffic Management issues

#1
Why is the latest news update for Cranwell still showing traffic management issues? I assumed that mean't road/pathway works were impeding BT Openreach - if this is true that has finished in Cranwell 2 weeks ago (Path being relaid BT LCC).If mot what is the issue ?
Plus I has some BT/BT OpenReach gents on my land BEFORE christmas doing a survey as Cranwell had been chosen to take part in FTTH using existing BT telegraph poles - can you comment on this

Thanks
Clive
#2
Good Morning Clive,

The Traffic Management is concerning some duct blockages we still have and we are negotiating with Highways to allow us to work at specific times.

We have previously deployed overhead fibre elsewhere in the county, so we will look to utilise any existing route where possible before we build new new duct lines.

Regards
Steve