Billinghay

#1
Hi Steve,

We spoke via e-mail back in July regarding Billinghay, some of the village is I believe live but some of the other cabinets including cabinet 6 are due later in the project. Given the excellent progress to date I just thought I'd ask whether there is any likelihood of this cabinet being completed prior to the middle of next year?

Thanks,

Stephen
#2
Hi Stephen,

Thanks for writing in to us.

We are scheduled to complete this cabinet by the end of this calendar year. I haven't got a specific date, but it is now in the plan for this Quarter.

We will update the website as soon as it goes 'Live' (normally on Friday afternoons).

Regards
Steve

#3
Hi Steve,

Just a short note to see whether cabinet 6 at Billinghay is still in the plan for this year?

Thanks again,

Stephen
#4
Good Morning Stephen,

At this point in time, BT are sticking with the line that this cabinet will be delivered by the end of this calendar year.

Should anything change, we will update this site, but at this point, it looks good to go.

Regards
steve
#5
Hi Steve,

I presume as it is getting near to Christmas and the inevitable slow down and as yet no activity around cabinet 6 at Billinghay it must have slipped a bit?

Thanks,
Stephen
#6
Good Morning Stephen,

Thanks for writing in.

We are having some difficulties with the fibre feed into Billinghay which might cause some minor delays. BT are telling me early New Year, but are still trying to complete before 31st December. I hope to get a more accurate update by the middle of this week and we will update the website when we have more definate news.

Regards
steve
#7
Hi,

Happy New Year.

When time and opportunity permits would it be possible to get an update on Billinghay cabinet 6. As far as I can see no cabinet has been stood yet so I presume there is a delay with this and other cabinets in the area linked to the above but just wanted to confirm the latest.

Thanks,
Stephen
#8
Hi

From the post code checker I understand Billinghay 6 is due for the current quarter but just wanted to enquire about progress as the last update I received stated that a location needed to be agreed with the developers. On a couple of occasions I have seen white spray paint on the road from BT Openreach but this then slowly fades and nothing else seems to happen.

Broadband in this part of the village has worsened quite significantly over the last few months, especially at peak times so I'm looking forward to when this becomes a reality.

Thanks

Stephen
#9
Good Morning Stephen,

Thanks for getting in touch with us.

I have sent your enquiry to BT and will get back to you as soon as I get a response.

Regards
Steve
#10
Hi,

Any further developments in relation to Billinghay Cabinet 6 - has this been moved into another phase? I know there are issues with this but if originally it was in plan for end of calendar year 2014 it is now well delayed.

Thanks,
Stephen
#11
hi, sorry to chase but any updates?

Thanks,
Stephen
#12
Good Morning Stephen,

Thanks for getting back to me. I will ask BT when we meet tomorrow and qwe will post the information on our weekly updates.

Regards
Steve
#13
Hi Steve,

Was there any update from BT on this? What phase is this cabinet now in?

Thanks,
Stephen
#14
Hi Stephen,

BT had no further updates last week, but I will send another enquiry now and try to get a firm date.

Regards
steve
#15
Hi Steve
on a similar issue issue, what's BT's update on Digby?
regards
R A Rogers