Friskney

#1
Can you ask BT if the new Fibre Cabinet will be in the same place as the old cabinet as the work they are doing and pulling fibre through seems to go the opposite way then one would expect, and if possible can they give me a completion date please
#2
Good Morning Tim,

BT will normally locate the new cabinet within 50 metres of the old where possible. Rarely, they may go a little further but where possible, they put them as close as possible. every situation is different in terms of potential and available locations.
Locally, they may well be feeding cabinets further along the same run, or feeding to the new cabinet site.

With regard to timescales, they are still sticking with the end of this calendar year and we have no news to the contrary. I will speak with them on Thursday and see if I can get a more accurate completion date.

Regards
Steve