Project Update - Week Beginning 30th March 2015

30th March 2015

 

Phasing datesPhasing 4-5

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Completed cabinet list

Cabinet 3 on the BINBROOK exchange

Cabinet 68 on the BOSTON exchange

Cabinet 1 on the CORRINGHAM exchange

Cabinet 1 on the FRISKNEY exchange

Cabinet 4 on the FRISKNEY exchange

Cabinet 1 on the GAINSBOROUGH exchange

Cabinet 81 on the GRANTHAM exchange

Cabinet 2 on the HONINGTON exchange

Cabinet 3 on the HONINGTON exchange

Cabinet 35 on the LOUTH exchange

Cabinet 30 on the LOUTH exchange

Cabinet 1 on the MORTON exchange

Cabinet 4 on the NORTH KELSEY exchange

Cabinet 1 on the NORTH KELSEY exchange

Cabinet 7 on the SPILSBY exchange

Cabinet 3 on the STOW UNIT 3 exchange

Cabinet 3 on the SWALLOW exchange

Cabinet 12 on the WALTHAM exchange

Cabinet 16 on the WASHINGBOROUGH exchange

Cabinet 6 on the WOODHALL SPA exchange

 

 

Please note that we can only provide updates on delayed cabinets.

If you have any queries please contact us

 

Billingborough 3 Works are ongoing in terms of fibre optic cabling

Billinghay 1 –BT expects this to be RFS by the end of the month. Two weeks after this, products can be ordered from it.

Culverthorpe – Traffic management complete in Culverthorpe - Cuverthorpe 1 is ready in position and is powered.

Gosberton 5 –Blockages in ductwork. Resource will be made available when possible to complete this deployment

Holbeach St Johns 1 - Shifted in the plan. Now to be enabled July - September 2015

Horncastle 3 –This cabinet will be enabled in mid-April. 30th March Update: still on track

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Normandy By Spital 2 - This is delayed because the electric company needed to carry out surveys in relation to the power connection. It is stood and the fibre is connected so hopefully this won't be long.

Spalding 50 –Plan has been shifted out by a few weeks due to unforeseen delays – this cabinet will now be stood in April. 30th March Update - Still on track

Welton 9 – Engineering completed on Thursday 12th March – because of cabinet type, records will take longer to update. Please keep an eye on our completed cabinet list to see when this is enabled - Should be available for products soon

 Progree

 

 

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide