Project Updates

Project Update - Week Ending 03rd October

3rd October 2014

Since the last update another 1 cabinet has been enabled. This cabinet is listed below and covers an additional 527 premises. 51881 homes have been passed in total.

Cabinet 2 on the HECKINGTON exchange.

 

There has also been some additional information provided on some of the outstanding phase 2 cabinets:

Spalford Cab. 1 – Job had to be re-planned due to duct issues, planning is now complete and work can commence.

Scampton Cab. 4 – Power Wayleave now granted by Ministry Of Defence. Hope to install power connection in week commencing 6th October.

Moulton Chapel Cab. 1 – Requires Aerial fibre cable. New sites for poles have been agreed so work can commence.

 

Over the coming week work will be carried out in or around the following areas providing Fibre Spine cables (From one Telephone Exchange to another):

Skegness, Burgh, Wainfleet, Spilsby, Butterwick, Stow, Withern, Honington, Ingoldby, Sutton on Sea, and Swaby.

In addition, we will be continuing to work on various cabinets in other areas of the county.

Please note that this is not an exhaustive list and is for indication only.

 

 

Progress Thermometer 26.09.14

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provider.