Project Updates

Project Update - Week ending 10th July 2015

10th July 2015

Phasing datesPhasing 6-7

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible

 

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet 3 on the ANCASTER exchange

Cabinet 1 on the LAUGHTON exchange

Cabinet 2 on the MARTIN exchange

 

Please note that we can only provide updates on delayed cabinets.

 

If you have any queries please contact us

 

Delayed cabinets

Ancaster 4 – Natural England now given Ok to start. Traffic management applied for to start works. 5.4Km of network to cable. 05/06/15 No Change – awaiting traffic management permission. 12/06/15 Cabling has been started and is ongoing 03/07/15 Cabling is ongoing 10/07/15 Cabling ongoing 4K  completed 1.5K left  

Bainton 4 –Currently with planners, BT will push for early completion 05/06/15 BT are chasing planners for progression 12/06/15 Still with planning team 03/07/15 No change in situation 10/07/2015 No change, BT chasing planning for a resolution

Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December 10/07/15 Meeting held again this week Ref New Duct over bridge Oct - Dec still completion period

Billingborough 1 - Cabinet 1 has some planning delays associated and BT are moving to resolve as soon as possible. We will update within the next week or so on progress. 10/07/15 Planning issues are still being dealt with. We are hoping to have timescales for this in the coming weeks

Billingborough 5 – currently taking orders but we are aware of issues associated with this cabinet and Billingborough 5 and are trying to remedy these as soon as possible

Birchwood 38 - New duct laid and blown fibre tubing provided. Cab stand with contractor. Will urge for completion early July. 10/07/15 Cabinet will be stood between now and the 18th July

Birchwood 63 - DELAYED – this cabinet will not be completed until quarter of October - December

Birchwood 72 - Just needs copper and Light - should be completed before the end of this month. 10/07/15 Cabinet has a land wayleave issue but the entire network is proven.

Bottesford 5 – Should be completed by the end of the month. Just needs fibre linking up to it. 10/07/15 Looking to connect fibre this Sunday

Buckminster 7 - Road crossing was completed at the weekend and now working on cabling    

Chapel St Leonards 12 – Shifted in plan. Now expected to be excepting orders in August, 10/07/15 – no change

Corby Glen 1 & 2 – Traffic management authorisation has caused these to be delayed. Set to be delivered this quarter, before the end of September.   10/07/15 Traffic management issues remain. Trying to rectify

Cranwell 2 - Delays linked to Ministry of Defence property and survey for Dslam now complete and with planning. 10/07/15 No change

Cranwell 5 – No longer shifted to August -  this cabinet should be enabled before the end of the month as now only needs fibre connecting to it. 10/07/15 POSSIBLE DELAY The structure may need to be moved.

Folkingham 1 – this cabinet should be enabled before the end of the month 10/07/15 No change

Folkingham 3 – shifted slightly in plan due to delays. Should be enabled before the end of September 10/07/15 No change

Fulbeck 3 – this cabinet should be enabled before the end of the month. Just needs fibre feeding to it. 10/07/15 Still Aiming for end of Month. Cabling and trenching ongoing

Gosberton 5 – BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack. 05/06/15 No change 12/06/15 – overlay works have been issued to engineers. 03/07/15 ongoing 10/07/15 Ongoing Will has asked for meeting with highways and Bridge people to try and move it forward

Grantham 16 - New duct on Road Crossing requiring a road closure. Engineers are still waiting for dates for when this can be completed. 10/07/15 No Change

Grantham 21 – Just needs power and Light - completion July

Grantham 34 – 500mts power which will delay enablement until July according to Western Power. 12/06/15 No change 03/07/15 works are with Western Power 10/07/15 No Change

Holbeach St Johns 1 - DELAYED – Will not be complete until July – September 10/07/15 No Change

Honington 1 – power provision ongoing – long route which has meant delays. 10/07/15 Power connection date 15th Aug

Honington 603 – this cabinet should be enabled by the end of the month. Currently awaiting power connection and certification. 10/07/15 Power connection was booked in for yesterday

Horsington R1 – Ready for Service. Should be accepting orders in the coming weeks.

Kirton 5 (amalgamated with 13) - work is with the engineers and is still pending. 05/06/15 No change 12/06/15 Awaiting overlay works for copper cable 03/07/15 ongoing 10/07/15 Still Waiting Duct work to Link these

Knipton 1 & 3 – these cabinets should be enabled by the end of the month. 10/07/15 Duct works continuing at present

Langrick 1 – DELAY linked to new duct over bridge which requires various meeting with Bridge engineers and Contractors. 10/07/15 Meeting held this week to try and progress duct over Bridge

Langrick 2 – this cabinet should be enabled by the end of the month

Lincoln 76 - this cabinet should be enabled by the end of the month

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Lincoln 133 - New duct required between existing cabinet and new cabinet 03/07/15 - ongoing 10/07/15 Waiting for job to come through from planning to deal with copper ties

Old Leake 1, 3, 4, 5, 6 – DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages. 10/07/15 Still progressing with blockage clearance. Old Leake 5 will be considerably delayed as a road closure required for this which requires 13 week notice.

Normanby By Spital 2 – High cost power - quote approved; with WPD 10/07/2015 Just waiting power

Risegate 3 – should be ready to take orders in the coming weeks. This cabinet is ‘ready for service.’ Waiting for computer systems to be updated. 10/07/15 All work completed just waiting for the resolution of a systems issue

Sleaford 28 - Looking to use an existing fibre to expedite delivery. This cabinet should be completed by the end of this quarter, before the end of September. 10/07/15 No Change

Spalding 50 – Shuttering complete. With WPD to resource. End june / early July 10/07/15 No Change

Spalding 16 & 26 – DELAYED. Should be completed by the end of this quarter, before the end of September 10/07/15 No Change

Spalding 45 – DELAYED. Will be completed towards the end of this quarter, around September time. 10/07/15 one section of Duct overlay (overhead wiring) required

Spilsby 1- only requires copper and fibre feeding to it now. Should be completed soon. 10/07/15 The cabinet may need to be moved - meeting with highways

Sudbrooke Park 18 – Direct labour engineers on with now, expected delievery 1st week of July 10/07/2015 Cabling delayed on final section linked to TM

Wickenby 2 – works are currently progressing to feed fibre to new structure. 10/07/15 The cabinet is due to be stood between the 14th and 24th June. All ducting has been proved. 88m of fibre remaining to be jointed.

Withern 1,3 & 4 - these cabinet should be enabled by the end of the month 10/07/15 Still on target but one cabinet is waiting a duct overlay (overhead wiring) section.

 

 

progress july

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide