Project Update - Week ending 10th March 2017

10th March 2017

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in timeBT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

  • Risegate 4

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Bourne 32 - Stood in position, coppered, powered and certificated. Road crossing required for fibre to be installed; Traffic Management delayed by 1 week (now w/c 27th Feb), still expected to be live mid March.

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit, replanning required, date of planning slot has not yet been provided.

Gosberton 5 – All new poles and aerial cable erected; just need Traffic Management for jointing on the bridge, TM did not go ahead this week, but still expected to be live mid March.

Holbeach St Johns 1 - Issue with the duct route; 300m of new duct required, date for this work to be confirmed; completion still expected by the end of March. 

Spalding 16 – Land owner looking at wayleave agreements before work can commence

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide