Phasing datesPhasing 7

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice


Cabinet 19 on the BOURNE exchange

Cabinet 4 on the CORBY GLEN exchange

Cabinet 6 on the FULBECK exchange

Cabinet 2 on the FULSTOW exchange

Cabinet 23 on the MARKET DEEPING exchange

Cabinet 28 on the MARKET DEEPING exchange

Cabinet 6 on the METHERINGHAM exchange

Cabinet 26 on the SPALDING exchange

Cabinet 45 on the SPALDING exchange

Cabinet 2 on the SWATON exchange

Cabinet 2 on the WITHAM ON THE HILL exchange



If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

Bainton 4 – new duct job with contractor. Estimated completion date 16/12

Bassingham 4 - Power connection on BT land. Property manager to agree. Estimated completion date 16/12

Billinghay 6 - Issue with duct blockage. Estimated completion date 23/12

Birchwood 63 - Estimated completion date 16/12

Burgh on Bain 3 - Programmed for 31/12

Burgh on Bain 4 - Still has outstanding wayleave issue for power

Caistor 9 - Estimated completion date 16/12

Chapel St Leonards 12 – Estimated completion date 16/12

Cranwell 2 - Awaiting return of power wayleave; then 2 weeks notice required for clearance to site. Estimated completion early January

Cranwell 5 – Build complete; with commissioners

Fulbeck 606 - Under review due to engineering difficulties and associated excessive costs

Gosberton 5 – No response from Network Rail; chased again.

Grantham 16 - Estimated completion date early January due to difficulty in completing civils activity in advance of cab shift.

Grantham 21– New power date 15/12

Grantham 34 – Issue with power pit, chasing up new estimated completion date

Holbeach St Johns 1 - Expected January due to additional civils issues.

Huttoft 1 - Estimated completion date 23/12; 2 overlays to complete then cabling and jointing of spine

Huttoft 3 - Estimated completion date 23/12; 2 overlays to complete then cabling and jointing of spine

Kirton 5 - Expected January due to additional civils issues.

Kirton 8 - Civils delayed due to other utility in the area, Highways agreed new start date of 16/12; Estimated completion date 30/12

Lincoln 76 - Estimated completion date 2312, chasing power date

Lincoln 132 – Estimated completion date 9/12, chasing power date

Lincoln 133 - New duct required to be laid - estimated completion date still 23/12

Long Sutton 4 - Estimated completion date 16/12

Metheringham 1 - Traffic management issue, estimated completion date mid-January

Metherinham 14 - Estimated completion date 16/12

Old Leake 6 – Quality issue with civils work, will need a large amount of re-work - estimated completion date to January

Normanby By Spital 2 – Issue with power pole, estimated completion date 23/12

North Somercotes 3 - Cabinet has been moved to facilitate new development. Estimated completion date 23/12

South Cockerington 2 - Estimated completion date 30/12; several overlays in progress, spine cabling and jointing to follow over Xmas period

South Cockerington 3 - Estimated completion date 30/12; several overlays in progress, spine cabling and jointing to follow over Xmas period

Spalding 50 – On-going power issue, estimated completion date 23/12.

Spalding 16– Estimated completion date mid-January; additional blockages found

Spilsby 1 - Estimated completion date 16/12

Swaton 3 - Estimated completion date 23/12

Swinderby 1 - With commissioners, service availability imminent

Tetford EO (3) - Commissioning imminent

Withern 1 - Land ownership change has caused dispute over wayleave for pole. WPD to seek alternatives. Chasing update

 

November Progress

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide