Project Update - Week ending 11th September 2015

11th September 2015

Phasing datesPhasing 6-7

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet 76 on the Boston exchange

Cabinet 30 on the Bourne exchange

Cabinet 1 on the Dowsby exchange

Cabinet 2 on the Dowsby exchange

Cabinet 3 on the Dowsby exchange

Cabinet 1 on the Folkingham exchange

Cabinet 1 on the Marshchapel exchange

Cabinet 2 on the Marshchapel exchange

Cabinet 2 on the North Somercotes exchange

Cabinet 3 on the Saltfleetby exchange

Cabinet 3 on the Sibsey exchange

Cabinet 1 on the Sutton Bridge exchange

Cabinet 4 on the Torksey exchange

Cabinet 4 on the Withern exchange

 

If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

 

Ancaster 4 – Ready for service -  CRFS shortly DELAY - issues have arisen in getting this to CRFS. Escalated for urgent resolution

Bainton 4 – Position agreed by Highways Authority and Town planners have agreed to early start on this. Processes being expedited to make sure it gets to RFS ASAP

Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December; new duct required over the bridge

Billingborough 1 - Cab site surveyed, location agreed with Highways Authority; with Contractors to stand and then we will joint, expected late this quarter / early next. 04/09/15 Blown fibre tube to joint box - with engineers to stand the cabinet 11/09/15 Power connection will be made 23rd September

Billingborough 5 – Cab site surveyed, location agreed with Highways Authority; with Contractors to stand and then we will joint, expected late this quarter / early next 04/09/15 - dependant on Billingborough 1

Birchwood 63 - DELAYED – this cabinet will not be completed until quarter of October. BT cabling late August (half completed)

Buckminster 7 - Overlay works (on poles) required expected delivery in this quarter, before the end of September. DELAY - Delays in cabinet build due to agreement of Sunday working/road closure. Likely completion mid-October

Chapel St Leonards 12 – Shifted in plan. Wayleave still outstanding with developer

Corby Glen 1 & 2 – Traffic management authorisation has caused these to be delayed A1+ will not let BT in to clear blockages & cable until the 7th September, should be available mid-September. Blockages on A1 cleared - likely to be ready for service next week. Two weeks after this products can be ordered from this cabinet

Cranwell 2 -  This cab is planned and job has been designated to the engineers to stand. Cabinet stand and completion is forecast for next quarter

Cranwell 5 – Second survey completed, awaiting formal survey return. Delivery forcast for next quarter

Folkingham 3 – Fibre damaged by others. BT fibre jointers are working on this today 04/09/15 Will be RFS next week - 2 weeks after this services can be ordered.11/09/15 DELAY - power now due 23rd September. Completion of cabinet likely October

Gosberton 5 – 11/09/15 Contractor have had site visit and will be submitting the required documents to Network Rail

Grantham 16 - SHIFTED - Expected delivery between October and December

Grantham 21– 11/09/15 Position for power has not yet been agreed

Grantham 34 – Chasing new date with power company for works under traffic management - chasing today 04/09/15

Holbeach St Johns 1 - DELAYED - All poles erected at the weekend, waiting remedial civils work likely to be RFS October - November due to size of the PON

Honington 1 – Power provision ongoing – long route which has meant delays. Waiting on WPD for a connection date. 04/09/15 Road crossing and power delivery due to be completed this week 10/09/15 with commissioners. Should be ready for orders in approximatly 2 weeks

Kirton 5 (amalgamated with 13) - Should be RFS early October as big copper job (De-load / Re-load with cab 13)

Knipton 1 & 3 – Outstanding civils - Expected to be cleared by End of August 04/09/15 blockages should be cleared this week. 11/09/15 Expected to be ready for service next week - two weeks after this products can be ordered from it

Langrick 1– DELAY linked to new duct over bridge which requires various meeting with Bridge engineers and Contractors. 1KM of duct work to go over a deep dyke. In progress

Langrick 2 – power connection date will be 23/09/15

Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015

Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015

Lincoln 133 - Cab up and powered, needs copper and fibre, but new duct required which could cause further delay

Metheringham 1 Due to be supplied with power 12th October

Metheringham 6 - Cabinet stood in position. With planners to provide route utilising existing fibre 11/09/15 Due to be supplied with power 12th October

Old Leake 1, 3, 4, 5, 6 – DELAYED –  cabinets 1,3,4 and 5 should be ready for service at the end of September. Two weeks after this services can be ordered. Cab 6 will be delayed further as a new duct needs to be installed. 11/09/15 no change - 1,3,4 and 5 should be RFS next week

Normanby By Spital 2 – High cost power - quote approved; Power wayleaves required

Sleaford 28 - Looking to use an existing fibre to expedite delivery. This cabinet should be completed by the end of this quarter, before the end of September

Spalding 50– New point of connection point found; with the engineering team to be programmed with Western power

Spalding 16 & 26– DELAYED - Completion will probably be in November, new duct required

Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December

Spilsby 1- DELAYED - De-load / Re-load and road closure. Next quarter delivery

Swaton 2 & 3 Location for cabinet 3 has been rejected so planning works for this are ongoing - this has gone back for re-survey. Cabinet 2  is in job list to stand

Wickenby 2 – Chasing for power date 11/09/15 Due to long lengths of cabling required, the first power connection date available is 22/10/15

Withern 1- Withern 1 requires power wayleaves which are being chased today 11/09/15

Witham on the Hill 1 & 2 Witham 1 is expected to be ready for service at the end of September. Witham 2 requires a cabinet stand date.

 

Progress September

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide