Project Update - Week Ending 12th December 2014

12th December 2014

phasing 3-4

Since the last update another 14 cabinet have been enabled which covers an additional 2414 premises.

 

UPDATE 15/12/2014 - SCAMPTON 4 IS READY TO TAKE ORDERS


Cabinet 1 on the ALFORD exchange

Cabinet 44 on the BIRCHWOOD exchange

Cabinet 8 on the CHAPEL ST LEONARDS exchange

Cabinet 103 on the LINCOLN exchange

Cabinet 92 on the LINCOLN exchange

Cabinet 82 on the LINCOLN exchange

Cabinet 18 on the LINCOLN exchange

Cabinet 129 on the LINCOLN exchange

Cabinet 31 on the SKEGNESS exchange

Cabinet 40 on the SKEGNESS exchange

Cabinet 27 on the SKEGNESS exchange

Cabinet 3 on the SUTTON ON SEA exchange

Cabinet 8 on the SUTTON ON SEA exchange

Cabinet E2 on the WOODHALL SPA exchange

 

 

Cabinet progress update

Billinghay 1 BT have said that Traffic Management is required and that there are multiple blockages to contend with. This is going to be delayed for a significant time

Coningsby 4 – Work is going to begin on Wednesday to cable this cabinet up using the alternative Point of Connection, avoiding the asbestos.

Cranwell 4 – Traffic management issues have caused unforeseen delays on this cabinet which will unfortunately not be completed before the end of December.

Friskney cabs x 4 –Multiple blockages have been identified on all legs of the spine cable feeding Friskney. Engineers are trying to clear them but this will not be a quick job. Unable to supply time frame

Grantham 5 - Ready for service,’ should be customer ready within the next two weeks.

Grantham 81 – All the fibre tubing is installed – engineers need to position the cabinet which might have to wait until after December.

Horncastle 3 - New location agreed with the Highways Agency, all planned for deployment now

Heckington 1 – 21m of new ducting required; looking to have completed by the end of December

Moulton Chapel 1Ready for service’ on 16th December. Should be customer ready two weeks after this date

Scampton 2 – Delayed due to the work on new bus stops on the same route as the new duct. However, the  new duct being installed Saturday 13th December

South Rauceby 1 – South Rauceby spine is sub-ducted and ready to have fibre inserted. Electric works planned. South Rauceby 1 & 2 are now priority.

South Rauceby 2 – Road is now confirmed as adopted and work is ongoing

Spalding 50 – Due to unforeseen delays this cabinet is not going to be stood until the middle of January

Spalford 1 – BT expect this to be 'ready for service' (RFS) Friday 12th December – two weeks after this it will be ‘customer ready for service’ and products can be brought from it.

Sudbrooke 11Ready for service,’ should be customer ready within the next two weeks.

Wainfleet 4 – Error reported – was said to have been Ready for service’ last week but has only just been registered as so this week. Should be ready for customers in the next two weeks. Apologies, misinformation provided to the team.

Withern Cabs x 2 – Estimated completion date of 7th February 2015

 

Progress Thermometer December

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide