Project Update - Week ending 12th February 2016

12th February 2016

Phasing datesphasing 8

 

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Cabinet 6 on the Billinghay exchange

Cabinet 133 on the Lincoln exchange

Cabinet 38 on the Louth exchange

Cabinet 1 on the Spilsby exchange

Cabinet 6 on the Old Leake exchange

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Delayed cabinets

Bassingham 4 – Power certification complete, now with commissioners; services should be available within 2 weeks

Burgh on Bain 4 - Power connection re-booked for 02/03/16

Cranwell 2 - Cabinet is now powered. Estimated completion 17/02/16

Corby Glen 5 – Power connection booked 23/02/16; estimated completion date 24/02/16

Fulbeck 606 - Will be added back in programme following review

Gosberton 5 – Trial digs arranged for 23/2. If successful passive optical network (PON) will be delivered 17/3

Grantham 16 - Due to difficulty in completing civils activity in advance of cab shift. This has become more delayed - estimated completion 02/03/16

Grantham 34 – Power connection booked 29/02/16

Greatford 5 - delayed as duct damaged during roadworks; estimated completion date 17/02/16

Holbeach St Johns 1 - Expected mid-February due to additional civils issues.

Huttoft 1 - Further delay due to water pipe damage in vacinity of planned civils; estimated completion date 02/03/16

Huttoft 3 - Further delay due to water pipe damage in vacinity of planned civils; estimated completion date 02/03/16

Kirton 5 - Highways issues with civils work - expected completion date 09/03/16

Kirton 8 - Highways issues with civils work - expected completion date 09/03/16

Lincoln 50 - Lane closure agreed with Lincs Highways Authority. Expected completion 28/02/16

Lincoln 76 - Estimated completion date 25/02/16

Lincoln 132 – Estimated completion date 25/02/16

Metheringham 1 - Traffic management re-booked estimated completion date shifted 09/03/16

Metheringham 3/2 (Nocton) - Estimated completion 31/03/16

Metherinham 14 - PLEASE NOTE - there is a computer records issue here currently being resolved by an expert but there may be slight additional delay; should be resolved by 24/02/16

North Somercotes 3 - Estimated completion date 02/03/16

Owersby Moor E4 - duct issue under railway. Awaiting quote from contractor.

Normanby By Spital 2 – Issue with power pole, power connection booked 18/02/16

Spalding 16 – Estimated completion 10/03/16 due to additional blockages

Withern 1 - No change – alternative solution to power being sought

 

January progress

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide