Project Update - Week ending 12th June 2015

12th June 2015

Phasing datesPhasing 5-6

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for 20% of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible

 

 

Completed cabinet list


Cabinet 24 on the BOURNE exchange

Cabinet 1 on the GREAT PONTON exchange

Cabinet 1 on the LONG BENNINGTON exchange

Cabinet 2 on the LONG BENNINGTON exchange

Cabinet 36 on the LOUTH exchange

Cabinet 37 on the LOUTH exchange

Cabinet 20 on the MARKET DEEPING exchange

Cabinet 3 on the NORTH KELSEY exchange

Cabinet 6 on the SCOTTER exchange

Cabinet 12 on the SKEGNESS exchange

Cabinet 39 on the SKEGNESS exchange

Cabinet 36 on the SPALDING exchange

 

Please note that we can only provide updates on delayed cabinets.


If you have any queries please contact us

 

 

Delayed cabinets

Ancaster 4 – Natural England now given Ok to start. Traffic management applied for to start works. 5.4Km of network to cable. 05/06/15 No Change – awaiting traffic management permission. 12/06/15 Cabling has been started and is ongoing
 
Bainton 4 –Currently with planners, BT will push for early completion 05/06/15 BT are chasing planners for progression 12/06/15 Still with planning team
 
Billingborough 5 – 1 Blockage left but this needs 3 way lights required (applied for). 05/06/15 Traffic lights booked for Friday 5th June 12/06/2015 – should be completed by the end of this month
 
Billingborough 3 – 1 Blockage left but this needs 3 way lights required (applied for). 05/06/15 Traffic lights booked for Friday 5th June 12/06/2015  This is due to be 'ready for service' soon –  approximately 2 weeks products can be ordered from this cabinet
 
Birchwood 72 - Cabinet stood in position, works are ongoing to get this ready for service 05/06/15 Cabinet is now powered and BT will be booked in copper and fibre works. 12/06/15 – issue with cabinet location. Waiting for this to be resolved
 
Gosberton 5 – BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack. 05/06/15 No change 12/06/2015 – overlay works have been issued to engineers
 
Grantham 21 – Power connection needs completing. Liaisons ongoing with the power company. 29/05/15 Traffic Management required for power road crossing, being organised. 12/06/15 No change
 
Grantham 34 – 500mts power which will delay enablement until July according to Western Power. 12/06/15 No change
 
Holbeach St Johns 1 - DELAYED – Will not be complete until July – September
 
Horncastle 3 – Duct work programmed/noticed this week, Power connection still required. 29/05/15 waiting for next possible date for power connection. 12/06/15 This cabinet is expected to be complete by the end of the month – just awaiting power connection
 
Kirton 5 - work is with the engineers and is still pending. 05/06/15 No change 12/06/15 Awaiting overlay works for copper cable
 
Lincoln 132 – Shifted in the plan - due for deployment July – September 2015
 
Old Leake 3 – DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages 12/06/15 No change
 
Old Leake 6 - DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages 12/06/15 No change
 
Normanby By Spital 2 – Power outstanding but prioritised for delivery before the end of June. 12/06/15 Still waiting for power connection to be completed by power board
 
Sibsey 1- Cabinet position has been agreed – this cabinet should be ready for service by the end of June, products will be available approximately 2 weeks after this. 12/06/15 Still due for completion by the end of the month
 
South Rauceby 1 – New power quote received and authorised, in the plan for power to be connected next week. 29/05/15 Deep excavation is required. Shuttering to be provided by contractor for this. 05/06/15 Reports that roadworks are not booked until the end of this month are correct – a road crossing is required for the electric feed which is going to require significant engineering. Significant delays of at least another month unfortunately 12/06/2015 – Power to be provided starting on the 17th June  
 
Spalding 50 –Still waiting details from Power Company due deep excavations on power. 29/05/15 Deep excavation is required. Shuttering to be provided by contractor for this. 12/06/15 no change – still waiting on power
 
Sudbrooke Park 18 – Overlay is now complete, just needs the power to be certificated. 05/06/15 – Please accept our apologies for the ongoing delay on this cabinet. Unfortunately we were informed that all work was complete other than the power certification. This now seems to have been inaccurate and we now have to also complete both copper and fibre work at the cabinet. We will update as we progress'. 12/06/2015 one blockage left to clear then cabling work can be completed.

 



progress May 2015

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide