Project Updates

Project Update - Week ending 12th May 2017

12th May 2017

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in timeBT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

Cabinet 6 on the Stickney exchange
Cabinet 14 on the Waddington exchange 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit, replanning required. BT estimate planning to complete in September.

Holbeach St Johns 1 - Issue with the duct route; 300m of new duct required, further traffic management required, engineering work expected to be completed in early May. Fibre delivered yesterday to Lincoln. As soon as this is ok to Notice, it is first on the list to complete before any other job. BT estimate build completion in mid May.

Spalding 16 – Land owner looking at wayleave agreements before work can commence 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provider.