Since the last update another cabinet has been enabled.
Cabinet 3 on the FRISKNEY exchange
Cabinet progress update
Ancaster 2 – All traffic management is complete – this cabinet should be 'Ready for Service' shortly. UPDATE – still waiting for fibre jointing for connecting spine- ongoing
Ancaster 3 – All traffic management is complete – the cabinet now needs to be stood and for electrics to be provided. UPDATE – still waiting for fibre jointing for connecting spine- ongoing
Ancaster 4 - All traffic management is complete – the cabinet now needs to be stood and for electrics to be provided. UPDATE – still waiting for fibre jointing for connecting spine- ongoing
Billingborough 3 – delays are being caused due to blockages in the ducts for the Culverthorpe cabinets
Billinghay 1 – There are still traffic management issues and multiple blockages – This is expected to be ready towards to the end of the quarter (end of March.)
Billinghay 6 –There are still traffic management issues and multiple blockages – This is expected to be ready towards to the end of the quarter (end of March.)
Butterwick 3 – Not yet RFS (Ready for Service) – will be imminently. Approximately two weeks after this, products can be ordered from it.
Cranwell 4 – This cabinet will be 'Ready for Service' will be imminently. Approximately two weeks after this, products can be ordered from it.
Culverthorpe – Another section of 'zone of interest' has been identified. This means that the gas board will need to carry out a joint visit again to decide on the route for the ducting. Alternative routes are being considered.
Donington 6 – The existing fibre needs to be taken down overnight which will be happening on the 24th February
Friskney cabs x 3 – Friskney 2 should be 'Ready for Service' this week. Approximately two weeks after this, products can be ordered from it
UPDATE Friskney 1 - "This cabinet is waiting on power, no date set but is targeted for completion by end of March."
Grantham 81 – Cabinet is being positioned this week
Horncastle 3 –Have to re-survey for location as per Council instructions
Hubbard's Bridge 2 –Block on the Boston spine to Hubbards Bridge which is causing delays
Normanby by Spital EO Lines - All planned, waiting on the Copper / Fibre cab to be stood
South Rauceby 1 –Network Rail have given BT permission to proceed with works. BT are going to prioritise South Rauceby 1 to ensure it is completed as soon as possible – works are still ongoing
Spalding 50 –Cabinet will be stood 23rd February – other works will be required after this to connect power and join fibres
Spalford 1 – This is now 'Ready for Service'. In approximately two weeks, products can be ordered from this cabinet
Welton EO lines –Welton 9 is still ongoing – blockages are causing delays
Withern Cabs x 2 Delayed –Spine work completed but there are blockages in the duct to be cleared.
To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide
Enter your postcode in the box to find out how the Onlincolnshire campaign is making a difference to your community...
Test the speed of your broadband with the broadband speed checker