Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in timeBT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

Cabinet 1 on the Edenham exchange. 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Bourne 32 - Stood in position, coppered, powered and certificated. BT inform that the cabinet will be lit and sent to commissioning by Wednesday.

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit, replanning required. BT estimate planning to complete in September.

Gosberton 5 – Build complete. BT pre-commissioning checks in progress.

Holbeach St Johns 1 - Holbeach St Johns 1 - Issue with the duct route; 300m of new duct required, further traffic management required, engineering work expected to be completed in early May. Fibre delivered yesterday to Lincoln. As soon as this is ok to Notice, it is first on the list to complete before any other job. BT estimate build completion in mid May.

Spalding 16 – Land owner looking at wayleave agreements before work can commence 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide