Project Update - Week ending 15th April 2016

15th April 2016

Phasing datesphasing 8

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in time. BT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

There have been no additional cabinets enabled this week.

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice



Delayed cabinets

Burgh on Bain 4 - This is going to suffer significant delays - power booked in on the 12th May; DNO unable to improve date due to network upgrade

Dowsby 602 - Shifted - estimated completion now late April. Issue has arisen with steel duct which will be resolved next week

Fulbeck 606 - planning delay due to requirement to re-site the PCP. Delivery expected mid-May.

Gosberton 5 – trial digs planned for 18/4 as agreed with Network Rail and Highways. If successful then delivery expected early May

Grantham 16 - build complete. products will be available from this cabinet within 2 weeks

Holbeach St Johns 1 - moleploughing required on new planned route. ECD Late May.

Kirton 5 - Traffic management has delayed this - estimated late April

Kirton 8 - build complete. products will be available from this cabinet within 2 weeks

Lincoln 50 - late April estimation. New duct required.

Metheringham 3/2 (Nocton) - work commenced. ECD late April/early May.

Owersby Moor E4 - This cabinet has been removed from the project because of excessive build costs. There is a requirement for a directional drill to be completed and this alone would cost over £150K and on that basis, we cannot justify this level of expenditure. We will of course continue to seek alternative technological solutions for this area

Spalding 16 – early May ECD. New underground chamber required.

Progress April 2016

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide