Project Updates

Project Update - Week ending 15th July 2016

15th July 2016

Contract two phase one

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in time. BT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

Cabinet 29 on the Boston exchange

Cabinet 7 on the Caistor exchange

Cabinet 4 on the Hubberts Bridge exchange

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Dowsby 602 - Issues have been dealt with and cabinet will now be put forwards for re-commissioning

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit and there is more planning associated with doing this.

Gosberton 5 – Permissions granted from Network Rail. With planners now to implement changes to plans

Holbeach St Johns 1 - Timescales shifted - Moleploughing still ongoing at this time.

Metheringham 3/2 (Nocton) -All stood and powered and just needs fibre providing before commisioning

Spalding 16 – Discussions ongoing with property owner.

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide