Project Updates

Project Update - Week ending 15th May 2015

15th May 2015

Phasing datesPhasing 5-6

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Completed cabinet list

 

Culverthorpe 1
Hemswell 5
Spalding 53 

 

 

Please note that we can only provide updates on delayed cabinets.


If you have any queries please contact us

 

Delayed cabinets

Billingborough 5 – Blockage clearance attended, site goes into carriageway, unable to clear, 3 way lights required (applied for).  

Billingborough 3 – Blockage clearance attended site goes into carriageway unable to clear 3 way lights required (applied for).  

Billinghay 1 – BFT now completed, Blowing cable in starting on Monday, should be completed by end May.

Birchwood 72 - Cabinet not yet stood. Provisional date for this is the 27th May.

Culverthorpe – Culverthorpe 1 is now at CRFS, Culverthorpe 2 Dslam stood on 12/5, looking to programme in fibre and copper.

Gosberton 5 – BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack.

Grantham 21 – Power connection needs completing. Liaisons ongoing with the power company.

Grantham 34 – Dslam base down awaiting Dslam delivery (288’s), 500mts power which will delay until July according to Western Power.

Holbeach St Johns 1 - DELAYED – Will not be complete until July – September.

Horncastle 3 – Duct work programmed/noticed  this week, Power connection still required.

Kirton 5 - work is with the engineers and is still pending

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Old Leake 3 – DELAYED – Will not be complete until July – September. Spine is progressing but slowly working with TM clearing blockages.

Old Leake 6 - DELAYED – Will not be complete until July – September. Spine is progressing but slowly working with TM clearing blockages.

Navenby 4 – System updates ongoing - 50% complete.

Normanby By Spital 2 – Power outstanding but prioritised for delivery before the end of June.

Sibsey 1- Dslam programmed to be stood 27/5.

South Rauceby 1 – an alternative plan is now in place to source power – awaiting timescales for this.

Spalding 50 –Still waiting details from Power company due deep excavations on power.

Sudbrooke Park 18 – Shifted slightly in the plan - due to be completed before June 2015

Sutterton 3 – Power connected 12/5 just requires Test Cert

 

April 2015

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide