Project Updates

Project Update - Week Ending 16th January 2015

16th January 2015

Phasing 4-5

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

Since the last update another 3 cabinet have been enabled.

 

Cabinet 4 on the BUTTERWICK exchange

Cabinet 6 on the BUTTERWICK exchange

Cabinet 2 on the Scampton exchange

 

 

Cabinet progress update

Ancaster 2 –Traffic Management is underway to deal with blockages in spine ducting

Ancaster 3 – Traffic Management is underway to deal with blockages in spine ducting

Ancaster 4 - Traffic Management is underway to deal with blockages in spine ducting

Billinghay 1 – Traffic Management required – booked in to be organised

Billinghay 6 – This cabinet is situated on private land and BT are scheduling a meeting with the property developer to agree a position for the new cabinet. This isn’t expected to be ready until mid-February

Butterwick 3 –The existing copper infrastructure still needs to be reorganised – this work is with the engineers.

Cranwell 4 – Traffic management issues are still ongoing – this is being affected by the Ancaster cabinet Traffic management issues.

Culverthorpe 1 & 2 - Further multiple blockages near gas main requires joint visit with utilities

Friskney cabs x 4 – Blockage clearance underway. Cabinets will be stood this week

Grantham 81 – Cabinet is due to be stood in position soon. Power can then be connected.

Horncastle 3 – Overlay cables now required for powering up the cabinet – this is in hand

Heckington 1 –This was 'ready for service' 13th January, the cabinet will be able to have products brought from it approximately two weeks after this .

Normanby by Spital EO Lines - New ducting is now in place, and the cabinet just requires cabling and connecting to power.

South Rauceby 1 –Traffic management required due to railway line. Applications are being processed by Network Rail.

South Rauceby 2 –Cabinet is stood in position and is having power delivered to it on the 15th January.

Spalford 1 –Minor ducting works still required but majority of works completed

Welton EO lines –Welton 1 is complete –all of the records need to be updated onto the various BT systems. Welton 9 is currently ongoing

Withern Cabs x 2 – Estimated completion date of 7th February 2015 – this is still on track.

 

 

progress thermometer 090115

 

 

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide