Project Update - Week ending 16th October 2015

16th October 2015

 

Phasing datesPhasing 7

 Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependent upon demand. We are pushing BT to clear these issues as a matter of urgency, conscious that some cabinets are unavailable for an unacceptably long period. Please bear with us and additional capacity will be added as soon as possible

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet  6 on the  ANCASTER exchange

Cabinet  7 on the BILLINGHAY exchange

Cabinet  1 on the EAST KIRKBY exchange

Cabinet  3 on the FOLKINGHAM exchange

Cabinet  4 on the HONINGTON exchange

Cabinet 1 on the STENIGOT exchange

 

If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

 

Bainton 4 – Cabinet is being stood in position this week

Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December; new duct required over the bridge. 15/10/15 Bridge work to commence 12/11/15

Billinghay 6 - will be enabled next quarter, before the end of December

Billingborough 1 - Ready for service. In approx two weeks products can be ordered from this cabinet.

Billingborough 5 – Will be made live to Internet Service Providers once Billingborough 1 has gone live

Birchwood 63 - DELAYED – this cabinet will not be completed until October. BT cabling late August - ongoing

Buckminster 7 - Overlay works (on poles) required expected delivery in this quarter, before the end of September. DELAY - Delays in cabinet build due to agreement of Sunday working/road closure. Likely completion mid-October

Burgh on Bain 3 & 4 - cabinet are stood in position. Estimated completion end of November / mid-December

Chapel St Leonards 12 – No change but BT are meeting with the Developer (Keir Homes) next week

Cranwell 2 - This cab is planned and job has been designated to the engineers to stand. Cabinet stand and completion is forecast for next quarter

Cranwell 5 – Second survey completed, awaiting formal survey return. Delivery forecast for next quarter

Folkingham 4 - ready for service. Products should be available to order in approximately 2 weeks

Gosberton 5 – Overlay required over the bridge, Next quarter delivery

Grantham 16 - SHIFTED - Expected delivery between October and December. Civils work commenced 09/10/2015

Grantham 21– Cabinet is now stood and copper work is complete. Fibre work to be completed and testing/certification carried out

Grantham 34 – Chasing new date with power company for works under traffic management

Holbeach St Johns 1 - DELAYED - All poles erected at the weekend, waiting remedial civils work likely to be RFS October - November due to size of the PON

Huttoft 1 - works are currently in progress

Huttoft 3 - Fibre needs to be provided - estimated at the beginning of November

Kirton 5 (amalgamated with 13) - Should be RFS early October as big copper job (De-load / Re-load with cab 13)

Langrick 1– Expected physical completion early November

Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015

Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015

Lincoln 133 - New duct to be installed to allow provision of Copper and Fibre. Work commencing late October

Metheringham 1 Power connection date has had to be changed as a new source has been identified which required a road crossing - estimated for 12/11/15

Metheringham 6 - Power connection date has been changed - now estimated for 12/11/15

Old Leake 6 – Civils issues are ongoing

Normanby By Spital 2 – DELAY - cabinet failed commissioning tests. With Huawei to resolve

Sleaford 28 - RFS - products should be available to order in the coming weeks

South Cockerington 2  -  overlay works in progress (over poles)

Spalding 50– Engineers are booking in the power connection with their contractors - Date to be agreed.

Spalding 16 & 26– DELAYED - Completion will probably be in November, new duct required

Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December

Spilsby 1- DELAYED - De-load / Re-load and road closure. Next quarter delivery

Spilsby 4 - Just needs power and certification. Working with power company to get dates for this. Estimated for delivery 14/11/15

Swaton 2 & 3 - Next quarter delivery. HA originally rejected location for Swaton 3; we now have agreement on location.

Swinderby 1 - Cable recovery teams working to try to save the need to put in 3km of new duct. UPDATE - cable recovery team have been working on this for two weeks and works are progressing

Wickenby 2 – Road crossing for power. 22/10/15

Withern 1- Cabinet is stood, overlay for copper and light programmed in for this week. Estimation to be powered 22/10/15

Witham on the Hill. Cabinet 1 is ready for service - products should be available to order in approx 2 weeks. Witham 2 should be RFS approximately 06/11/15

October process

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide