Project Update - Week ending 17th February 2017

17th February 2017

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in timeBT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

No additional cabinet enabled this week


Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Bourne 32 - Stood in position, coppered, powered and certificated. Road crossing required for fibre to be installed; Traffic Management planned for week commencing 20th Feb, expected to be live mid March.

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit, replanning required, information on timescales wont be available until planning is complete

Gosberton 5 – All new poles and aerial cable erected; just need TM for jointing on the bridge, TM booked for week commencing 20th Feb, expected live mid March.

Holbeach St Johns 1 - Fibre cable was discovered to be damaged; new cable has arrived, but Traffic Management is required to be able to re-blow the cable; TM booked for 21st Feb 

Spalding 16 – Land owner looking at wayleave agreements before work can commence

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide