Project Updates

Project Update - Week Ending 17th April 2015

17th April 2015

 

Phasing datesPhasing 4-5

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Completed cabinet list

Cabinet 77 on the BOSTON exchange

Cabinet 8 on the CAISTOR exchange

Cabinet 87 on the LINCOLN

Cabinet 2 on the MORTON exchange

Cabinet 4 on the SUTTON BRIDGE exchange

 

 

Please note that we can only provide updates on delayed cabinets.

If you have any queries please contact us

 

Delayed cabinets

Billingborough 1 , 3  & 5 amalgamation - The spine and jointing will be complete by the end of April. The copper re-arrangement (and therefore the amalgamation of the cabinets) for 1 & 5 will be complete in mid-May

Billinghay 1 – Cabinet is stood in position and has power. Fibre optics are being fed to the cabinet at present. Possibly be RFS middle of next week – two weeks after the cab goes RFS products are available from it.

Culverthorpe – The fibre optic works are still ongoing in relation to these cabinets.

Gosberton 5 –Water Board authority required to feed the fibre optic cable across a bridge CORRECTION - Bridge is accross a train line - need Train Company permission. Other ducting issues have been associated with engineering works carried when raising this bridge and these are being investigated

Grantham 21 – Fibre optic cable to the cabinet requires completion. A road crossing is required in order to supply a power connection.

Holbeach St Johns 1 - Shifted in the plan. Now to be enabled July - September 2015

Horncastle 3 – Cabinet is stood but a new duct is required for Power

Kirton 5 - copper rearrangement is complete. Fibre optics now need providing to the cabinet – this work is with the engineers for completion.  

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Old Leake 3 – Traffice Management required to be able to feed fibre optics to the cabinet

Old Leake 6 -  Traffic management is required to replace damaged ducting -  this is an extensive piece of work and this cabinet will be delayed. 

Normanby By Spital 2 – Needs fibre optics feeding to cabinet and powering

Sibsey 1- 2km of new ducting which involved traffic management has been completed. Engineers are aiming to have this cabinet enabled ASAP and, at the latest before the end of June 2015

Spalding 50 –Plan has been shifted out by a few weeks due to unforeseen delays – BT is on track with current deployment

Sudbrooke Park 18 – Shifted slightly in the plan - due to be completed before June 2015

Sutterton 3 – Cabinet only waiting on power now – with the electric board.

Tetford 2 – Due for deployment early June

Navenby 4 - Expected to be RFS by the middle of next week. Two weeks after this, products can be ordered from it

 

 April 2015

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide