Project Updates

Project Update - Week ending 17th July 2015

17th July 2015

Phasing datesPhasing 6-7

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible

 

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet 2 on the BINBROOK exchange

Cabinet 45 on the BIRCHWOOD exchange

Cabinet E2 on the CORRINGHAM exchange

Cabinet 2 on the FOSDYKE exchange

Cabinet 1 on the FULSTOW exchange

Cabinet 114 on the LINCOLN exchange

Cabinet 3 on the RISEGATE exchange

Cabinet 3 on the SOUTH RAUCEBY exchange

Cabinet 1 on the TORKSEY exchange

Cabinet 2 on the TYDD exchange

 

Please note that we can only provide updates on delayed cabinets.

 

If you have any queries please contact us

 

Delayed cabinets

Ancaster 4 – Natural England now given Ok to start. Traffic management applied for to start works. 5.4Km of network to cable. 05/06/15 No Change – awaiting traffic management permission. 12/06/15 Cabling has been started and is ongoing 03/07/15 Cabling is ongoing 10/07/15 Cabling ongoing 4K  completed 1.5K left 17/07/15 - still ongoing

Bainton 4 –Currently with planners, BT will push for early completion 05/06/15 BT are chasing planners for progression 12/06/15 Still with planning team 03/07/15 No change in situation 17/07/15 No change, BT chasing planning for a resolution

Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December 10/07/15 Meeting held again this week Ref New Duct over bridge Oct - Dec still completion period

Billingborough 1 - Cabinet 1 has some planning delays associated and BT are moving to resolve as soon as possible. We will update within the next week or so on progress. 10/07/15 Planning issues are still being dealt with. We are hoping to have timescales for this in the coming weeks 17/07/15 - still awaiting timescales

Billingborough 5 – currently taking orders but we are aware of issues associated with this cabinet and Billingborough 5 and are trying to remedy these as soon as possible 17/07/15 No change

Birchwood 38 - New duct laid and blown fibre tubing provided. Cab stand with contractor. Will urge for completion early July. 10/07/15 Cabinet will be stood between now and the 18th July 17/07/15 Looking ready for infrastucture completion in four weeks

Birchwood 63 - DELAYED – this cabinet will not be completed until quarter of October - December

Birchwood 72 - Just needs copper and Light - should be completed before the end of this month. 10/07/15 Cabinet has a land wayleave issue but the entire network is proven. 17/07/15 No change

Bottesford 5 – Should be completed by the end of the month. Just needs fibre linking up to it. 10/07/15 Looking to connect fibre this Sunday 17/07/15 Infrastructure is complete. Should be able to accept orders in approx. 2 weeks

Buckminster 7 - Road crossing was completed at the weekend and now working on cabling 17/07/15 Sunday required for stand up of cabinet. Expected delivery in this quarter, before the end of September

Chapel St Leonards 12 – Shifted in plan. Now expected to be excepting orders in August, 10/07/15 – no change 17/07/15 Wayleave outstanding with developer.

Corby Glen 1 & 2 – Traffic management authorisation has caused these to be delayed. Set to be delivered this quarter, before the end of September.   10/07/15 Traffic management issues remain. Trying to rectify 17/07/15 A1+ insist on 3 month notice for blockages either side of A1. Expected delivery this quarter.

Cranwell 2 - Delays linked to Ministry of Defence property and survey for Dslam now complete and with planning. 10/07/15 No change

Cranwell 5 – No longer shifted to August -  this cabinet should be enabled before the end of the month as now only needs fibre connecting to it. 10/07/15 POSSIBLE DELAY The structure may need to be moved. 17/07/15 No change

Folkingham 1 – this cabinet should be enabled before the end of the month 10/07/15 No change 17/07/15 2 additional blockages to be cleared, cabinet expected to be live mid August.

Folkingham 3 – shifted slightly in plan due to delays. Should be enabled before the end of September 10/07/15 No change 17/07/15 no change

Fulbeck 3 – this cabinet should be enabled before the end of the month. Just needs fibre feeding to it. 10/07/15 Still Aiming for end of Month. Cabling and trenching ongoing 17/07/15 no change

Gosberton 5 – BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack. 05/06/15 No change 12/06/15 – overlay works have been issued to engineers. 03/07/15 ongoing 10/07/15 Ongoing Will has asked for meeting with highways and Bridge people to try and move it forward work still with Network Rail. 17/07/15 Chasing for meeting to agree way forward.

Grantham 16 SHIFTED- New duct on Road Crossing requiring a road closure. Engineers are still waiting for dates for when this can be completed. 10/07/15 No Change 17/07/15 SHIFTED - Expected delievery between October and December 2015

Grantham 21– Just needs power and Light - completion July 17/07/15 Power wayleave still required - chasing with power company

Grantham 34 – 500mts power which will delay enablement until July according to Western Power. 12/06/15 No change 03/07/15 works are with Western Power 10/07/15 No Change 17/07/15 chasing new date with power company for works under traffic management

Holbeach St Johns 1 - DELAYED – Will not be complete until July – September 10/07/15 No Change 17/07/2015 - no change

Honington 1 – power provision ongoing – long route which has meant delays. 10/07/15 Power connection date 15th Aug

Honington 603 – this cabinet should be enabled by the end of the month. Currently awaiting power connection and certification. 10/07/15 Power connection was booked in for yesterday 17/07/2015 - Power certification failed, secondary earth rod required, now expected live end August.

Horsington R1 – Ready for Service. Should be accepting orders in the coming weeks.

Kirton 5 (amalgamated with 13) - work is with the engineers and is still pending. 05/06/15 No change 12/06/15 Awaiting overlay works for copper cable 03/07/15 ongoing 10/07/15 Still Waiting Duct work to Link these

Knipton 1 & 3 – these cabinets should be enabled by the end of the month. 10/07/15 Duct works continuing at present 17/07/15 no change

Langrick 1– DELAY linked to new duct over bridge which requires various meeting with Bridge engineers and Contractors. 10/07/15 Meeting held this week to try and progress duct over Bridge 17/07/15 Meeting held and awaiting programme data from supplier

Langrick 2 – this cabinet should be enabled by the end of the month

Lincoln 76 SHIFTED- this cabinet should be enabled by the end of the month. DELAYED - Now expected late quarter 3, November - December 2015

Lincoln 132 SHIFTED – Shifted in the plan - due for deployment July – September 2015DELAYED - Now expected late quarter 3, November - December 2015

Lincoln 133 - New duct required between existing cabinet and new cabinet 03/07/15 - ongoing 10/07/15 Waiting for job to come through from planning to deal with copper ties 17/07/15 - delivery expected before the end of September

Old Leake 1, 3, 4, 5, 6 – DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages. 10/07/15 Still progressing with blockage clearance. Old Leake 5 will be considerably delayed as a road closure required for this which requires 13 week notice. 17/07/15 Cabinet 1,3 and 4 expected this quarter, before the end of September. Cabinet 5 requires road closure and 6 has extensive overlay requirements.

Normanby By Spital 2 – High cost power - quote approved; with WPD 10/07/2015 Just waiting power

Sleaford 28 - Looking to use an existing fibre to expedite delivery. This cabinet should be completed by the end of this quarter, before the end of September. 10/07/15 No Change 17/07/15 no change

Spalding 50– Shuttering complete. With WPD to resource. End june / early July 10/07/15 No Change 17/07/15 Pushing for power this quarter

Spalding 16 & 26– DELAYED. Should be completed by the end of this quarter, before the end of September 10/07/15 No Change 17/07/2015 no change

Spalding 45 DELAYED. Will be completed towards the end of this quarter, around September time. 10/07/15 one section of Duct overlay (overhead wiring) required 17/07/15 New position agreed to avoid wayleave - now likely to be delivered between October and December

Spilsby 1- only requires copper and fibre feeding to it now. Should be completed soon. 10/07/15 The cabinet may need to be moved - meeting with highways 17/07/15 SHIFTED Now will not be completed October - December as cabinet needs to be rebuilt.

Sudbrooke Park 18 – Direct labour engineers on with now, expected delievery 1st week of July 10/07/2015 Cabling delayed on final section linked to TM

Wickenby 2 – works are currently progressing to feed fibre to new structure. 10/07/15 The cabinet is due to be stood between the 14th and 24th June. All ducting has been proved. 88m of fibre remaining to be jointed. 17/07/15 Expected delivery this quarter, should be able to order services before September 2015

Withern 1,3 & 4 - these cabinet should be enabled by the end of the month 10/07/15 Still on target but one cabinet is waiting a duct overlay (overhead wiring) section. no change

 

 

progress july

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide