Project Update - Week ending 17th March 2017

17th March 2017

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in timeBT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

No additional cabinets completed this week.

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Bourne 32 - Stood in position, coppered, powered and certificated. Road crossing required for fibre to be installed; Blockages found on the fibre duct route, remedial works are booked in for this weekend. To lay the fibre next week, still expected to be live mid-March.

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit, replanning required, date of planning slot has not yet been provided.

Gosberton 5 – All new poles and aerial cable erected; Openreach operatives are currently working on this cabinet, it will be finished by the end of March.

Holbeach St Johns 1 - Issue with the duct route; 300m of new duct required, Openreach operatives are currently working on this cabinet, it will be finished by the end of March.

Spalding 16 – Land owner looking at wayleave agreements before work can commence 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide