Project Update - Week ending 18th December 2015

18th December 2015

Phasing datesPhasing 7

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Cabinet 26 on the BOURNE exchange

Cabinet 28 on the BOURNE exchange

Cabinet 27 on the BOURNE exchange

Cabinet 2 on the CROWLAND exchange

Cabinet 2 on the GREAT PONTON exchange

Cabinet 6 on the KNIPTON exchange

Cabinet 27 on the MARKET DEEPING exchange

Cabinet 4 on the MORTON exchange

Cabinet 3 on the MOULTON CHAPEL exchange

Cabinet 2 on the NEW LEAKE exchange

Cabinet 3 on the NEW LEAKE exchange

Cabinet 1 on the SWINDERBY exchange

Cabinet 3 on the TETFORD exchange

Cabinet 8 on the WAINFLEET exchange

 



If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

Bainton 4 – Shifted slightly - estimated completing date now 23/12/15

Bassingham 4 - Wayleave agreed, power connection to be booked. Likely completion early January.

Billinghay 6 - Issue with duct blockage. Estimated completion date 23/12

Birchwood 63 - Shifted slightly - estimated completion early January

Burgh on Bain 3 - Programmed for 31/12

Burgh on Bain 4 - Still has outstanding wayleave issue for power

Caistor 9 - Shifted slightly due to problems with light reading - estimated completion 23/12/2015

Chapel St Leonards 12 – Estimated completion date 16/12

Cranwell 2 - Awaiting return of power wayleave; then 2 weeks notice required for clearance to site. Estimated completion early January

Cranwell 5 – Build complete; with commissioners

Fulbeck 606 - Under review due to engineering difficulties and associated excessive costs

Gosberton 5 – No response from Network Rail; chased again.

Grantham 16 - Estimated completion date early January due to difficulty in completing civils activity in advance of cab shift.

Grantham 21– Estimated completion date 23/12/2015

Grantham 34 – Estimated for completion in January

Greatford 5 - delayed as duct damaged during roadworks. Expected delivery for February

Holbeach St Johns 1 - Expected January due to additional civils issues.

Huttoft 1 - Shifted slightly - expected delivery early January

Huttoft 3 - Shifted slightly - expected delivery early January

Kirton 5 - Expected January due to additional civils issues.

Kirton 8 - Civils delayed due to other utility in the area, Highways agreed new start date of 16/12; Estimated completion date 30/12

Lincoln 50 - BT Openreach and Highways are working towards a date to close the road. Cabinet on a busy street.

Lincoln 76 -Shifted slightly - expected delivery mid January

Lincoln 132 – expected delivery mid January

Lincoln 133 - Shifted slightly - expected delivery mid January

Long Sutton 4 - Physically complete, waiting for cabing to be registered on the system. Should be available for orders in two weeks.

Metheringham 1 - Traffic management issue, estimated completion date mid-January

Metherinham 14 - Shifted slightly - Estimated completion date 23/12/2015

Old Leake 6 – Quality issue with civils work, will need a large amount of re-work - estimated completion date to January

Normanby By Spital 2 – Issue with power pole, estimated completion date shifted to mid January

North Somercotes 3 - Estimated deliver mid-January

South Cockerington 2 - Estimated completion date 30/12; several overlays in progress, spine cabling and jointing to follow over Xmas period

South Cockerington 3 - Estimated completion date 30/12; several overlays in progress, spine cabling and jointing to follow over Xmas period

Spalding 50 – On-going power issue, estimated completion date shifted slightly to 30/12/15

Spalding 16– Estimated completion date mid-January; additional blockages found

Spilsby 1 - Estimated completion date shifted slightly to  23/12

Swaton 3 - Physically complete, waiting for cabing to be registered on the system. Should be available for orders in two weeks.

Withern 1 - Land ownership change has caused dispute over wayleave for pole. WPD to seek alternatives. No change - alternatives being sought


November Progress

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide