Project Updates

Project Update - Week ending 1st April 2016

1st April 2016

Phasing datesphasing 8

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in time. BT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

Cabinet 57 on the GRANTHAM exchange

Cabinet 8 on the GREATFORD exchange

Cabinet 1 on the HUTTOFT exchange

Cabinet 3 on the HUTTOFT exchange

Cabinet 7 on the MOULTON exchange

Cabinet 5 on the STICKNEY exchange

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Burgh on Bain 4 - This is going to suffer significant delays - power booked in on the 12th May; DNO unable to improve date due to network upgrade

Dowsby 5 - Ready for service - products will be available from this cabinet within 2 weeks

Dowsby 602 - Shifted - estimated completion now mid April

Fulbeck 606 - replan in progress. Estimated completion late April

Gosberton 5 – Continued issues on bridge have shifted timescales - estimated for late April.

Grantham 16 - Due to difficulty in completing civils activity in advance of cab shift. Continued access issues on the job. ECD 6th April

Holbeach St Johns 1 - Planning issue, survey required. ECD end of April

Kirton 5 - Traffic management has delayed this - estimated mid-April

Kirton 8 - Further civils issues encountered estimated completion date is now the end of April

Lincoln 50 - Cabinet stood; expected completion mid April

Metheringham 3/2 (Nocton) - Minor delay to delivery expected, meeting with sub-contractor held at site; new cabinet location agreed, fast-track documents with highways department. Traffic management beginning w/c 4th April.

Owersby Moor E4 - This cabinet has been removed from the project because of excessive build costs. There is a requirement for a directional drill to be completed and this alone would cost over £150K and on that basis, we cannot justify this level of expenditure. We will of course continue to seek alternative technological solutions for this area

Spalding 16 – Estimation shifted to mid April.

 

progress feb

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide