Phasing datesPhasing 5-6

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Completed cabinet list

Cabinet 1 on the HUMBERSTON exchange

Cabinet 1 on the HEMSWELL exchange

 

Please note that we can only provide updates on delayed cabinets.


If you have any queries please contact us

 

Delayed cabinets

Billingborough 5 – includes the amalgamated cabinet 1 lines. There is one blockage to clear in Billingborough now and estimations are that all works should be completed by the end of May

Billingborough 3 – just waiting for the fibre to be provided to the cabinet, however, there are multiple blockages in ducting (which required traffic management) in the ducts coming from Folkingham which, along with others, feed the Billingborough Cabinets. There is one blockage to clear in Billingborough now and estimations are that all works should be completed by the end of May

Billinghay 1 – DELAY – 844m of fibre remaining to lay. Traffic management to deal with this this began 30th April.

Birchwood 45 –expected to be ‘ready for service’ at the end of next week. Approximately 2 weeks after this products can be brought from it.

Culverthorpe – BT expect Culverthorpe 1 to be ‘ready for service’ next week – approximately 2 weeks after this products can be ordered from it. Culverthorpe 2 will be stood in position as a priority. Due to be completed before the end of June.

Gosberton 5 –BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack

Grantham 21 – Power connection needs completing. Liaisons ongoing with the power company.

Holbeach St Johns 1 - Shifted in the plan. Now to be enabled July - September 2015

Horncastle 3 – 8m of new duct needs to be installed; this is a priority for their contractors

Kirton 5 - work is with the engineers and is still pending

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Old Leake 3 – Extensive traffic management and civil engineering required, UPDATE - works on-going.

Old Leake 6 - Extensive traffic management and civil engineering required, UPDATE - works on-going.

Normanby By Spital 2 – Power outstanding but prioritised for delivery before the end of June.

Sibsey 1- Delivery of completed cabinet expected in June.

South Rauceby 1 -. Power planned for connection 30th April. UPDATE - Major issue with Power connection yesterday. BT had 3 engineers from the electric company and their engineers on site trying connect to the correct cable but the teams have encountered technical difficulties. May require another re-plan by the electric company for the correct power connection.

Spalding 50 –BT is on track with current deployment. UPDATE -  Spalding cabinet 50 is stood but it requires deep excavation & technical works for the power connection. The electric company are to schedule in joint site visit next week

Sudbrooke Park 18 – Shifted slightly in the plan - due to be completed before June 2015

Sutterton 3 – Power connection has been requested

Tetford 2 – Due for deployment early June

 

April 2015

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide