Project Updates

Project Update - Week Ending 20th March 2015

20th March 2015

 

Phasing datesPhasing 4-5

 

 

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

Since the last update another 13 cabinets have been enabled.

 

Cabinet 65 on the BIRCHWOOD exchange

Cabinet 10 on the BIRCHWOOD exchange

Cabinet 62 on the BIRCHWOOD exchange

Cabinet 1 on the CAISTOR exchange

Cabinet 4 on the CAISTOR exchange

Cabinet 5 on the CAISTOR exchange

Cabinet 39 on the GAINSBOROUGH exchange      

Cabinet 75 on the GRANTHAM exchange

Cabinet 163 on the GRANTHAM exchange              

Cabinet 7 on the HEMSWELL exchange     

Cabinet 1 on the INGOLDSBY exchange    

Cabinet 2 on the INGOLDSBY exchange    

Cabinet 3 on the INGOLDSBY exchange    

 

 

Cabinet progress updates

 

Please note that we can only provide updates on delayed cabinets.

The team are finding that the majority of cabinets are being enabled towards the very end of a phase, so the next influx will be towards the end of March for Phase 4 cabinets.

If you have any queries please contact us

 

 

ISSUES

South Rauceby 2 & product sign up- On investigation it seems this cabinet is full - BT aim to add further capacity on the 23rd March so please ensure you call your ISP soon after this date

 

DELAYED

Billingborough 3 Works are ongoing in terms of fibre optic cabling

Billinghay 1 –BT expects this to be RFS by the end of the month. Two weeks after this, products can be ordered from it.

Culverthorpe – Traffic management complete in Culverthorpe - Cuverthorpe 1 is ready in position and is powered.

Gosberton 5 –Blockages in ductwork. Resource will be made available when possible to complete this deployment

Holbeach St Johns 1 - Shifted in the plan. Now to be enabled July - September 2015

Horncastle 3 –This cabinet will be enabled in mid-April. Update: still on track

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Spalding 50 –Plan has been shifted out by a few weeks due to unforeseen delays – this cabinet will now be stood in April. Update: still on track

Welton 9 – Engineering completed on Thursday 12th March – because of cabinet type, records will take longer to update. Please keep an eye on our completed cabinet list to see when this is enabled

Progree

 

 

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide