Project Update - Week ending 20th May 2016

20th May 2016

 Contract two planning phase

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in time. BT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

Cabinet V3 on the Castle Bytham exchange

Cabinet 26 on the Market Deeping exchange

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Delayed cabinets

Burgh on Bain 4 - Power completed. BT expect this cabinet to be ready for service next week - two weeks after this orders can be made from this cabinet.

Dowsby 602 - Jointing in progress. The cabinet will then require commissioning.

Fulbeck 606 - Mid-May date shifted out. BT intend to move the cabinet so that it provides more benefit and there is more planning associated with doing this.

Gosberton 5 – Positons of poles agreed. Network Rail to sign off. Not expecting any issues and will push for completion ASAP

Holbeach St Johns 1 - Moleploughing required on new planned route. ECD Late May

Kirton 5 - Build complete, products will be available from this cabinet within 2 weeks - Update 20/05/16 - BT chasing this today

Kirton 8 - Completion date shifted as fibre needs providing to cabinet - build completetion estimate end of May

Lincoln 50 - Works agreed overnight for new ducting on the 26th June

Metheringham 3/2 (Nocton) -needs a new shell, job requires site meeting to determine if re-location is required. Notice has been given to carry out civil engineering at site.

Metheringham 3/1 (Dunston) - Cabinet stood, powered and coppered; De-silter on-site this week then fibre to be provided

Spalding 16 – This structure should be physically completed on the 1st June; will then require commissioning

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide