Project Update - Week ending 22nd January 2016

22nd January 2016

Phasing datesphasing 8

 

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

There are no cabinets to report as complete this week


If you have any queries please contact us

 

Delayed cabinets

Bainton 4 – Ready for service - orders can be made within one week

Bassingham 4 - Wayleave agreed, power connection booked for 27/1

Billinghay 6 - Shifted - estimated completion mid Feb

Burgh on Bain 3 - Build complete, just awaiting testing and commissioning

Burgh on Bain 4 - Power connection booked 29/01

Cranwell 2 - Awaiting return of power wayleave; then 2 weeks’ notice required for clearance to site. Estimated completion 10/2

Corby Glen 5 – Estimated completion end of February / beginning of March

Fulbeck 606 - Will be added back in programme following review.

Gosberton 5 – Contact has been made with National Rail. Requires road closure once plans are agreed

Grantham 16 - Due to difficulty in completing civils activity in advance of cab shift. This has become more delayed - estimated completion mid-February

Grantham 34 – Shifted - estimated mid-February

Greatford 5 - delayed as duct damaged during roadworks. Expected delivery for February

Holbeach St Johns 1 - Expected mid-February due to additional civils issues.

Huttoft 1 - Estimated completion date 3/2

Huttoft 3 - Estimated completion date 3/2

Kirton 5 - Shifted - expected mid-February. Delay in completing engineering

Kirton 8 - Civils delayed due to other utility in the area, Highways agreed new start date of 16/12; Estimated completion date 27/1

Lincoln 50 - Lane closure agreed with Lincs Highways Authority. Expected completion 28/2

Lincoln 76 - Estimated completion date 25/2

Lincoln 132 – Estimated completion date 25/2

Lincoln 133 - Estimated completion date 2/3

Louth 38 – estimated completion late March

Metheringham 1 - Traffic management booked, estimated completion date 3/2

Metherinham 14 - with commissioners, service availability expected within 2 weeks. PLEASE NOTE - there is a computer records issue here currently being resolved by an expert but there may be slight additional delay

Old Leake 6 – Quality issue with civils work, will need a large amount of re-work - estimated completion 27/1

Owersby Moor E4 - duct issue under railway. Awaiting quote from contractor.

Normanby By Spital 2 – Issue with power pole, power connection booked 18/2

North Somercotes 3 - Estimated completion date 19/2

South Cockerington 2 - with commissioners, service availability expected within one week

Spalding 16 – Estimated completion 12/2 due to additional blockages

Spilsby 1 -  Ready for service - orders can be made within one week

Withern 1 - No change – alternative solution to power being sought

 

 

January progress

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide