Phasing datesPhasing 5-6

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Completed cabinet list

 

Birchwood 37
Castle Bytham 2
Castle Bytham 4
Castle Bytham 5
Fulbeck 5
Sutton St. James 1
Torksey 2 

 

 

Please note that we can only provide updates on delayed cabinets.


If you have any queries please contact us

 

Delayed cabinets

Ancaster 4 – Natural England Now given Ok to start. TM applied for to start works,  5.4K of network to cable  

Billingborough 5 – 1 Blockage left but this needs 3 way lights required (applied for).

Billingborough 3 – 1 Blockage left but this needs 3 way lights required (applied for). 

Billinghay 1 – BFT now completed, Blowing cable in starting on Monday, should be completed by end May.

Birchwood 72 - Cabinet not yet stood. Provisional date for this is the 27th May.

Culverthorpe – Culverthorpe 1 is now at CRFS, Culverthorpe 2 Dslam stood on 12/5, looking to programme in fibre and copper.

Gosberton 5 – BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack.

Grantham 21 – Power connection needs completing. Liaisons ongoing with the power company.

Grantham 34 – 500mts power which will delay until July according to Western Power.

Holbeach St Johns 1 - DELAYED – Will not be complete until July – September.

Horncastle 3 – Duct work programmed/noticed this week, Power connection still required.

Kirton 5 - work is with the engineers and is still pending

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Old Leake 3 – DELAYED – Will not be complete until July – September. Spine is progressing but slowly working with TM clearing blockages.

Old Leake 6 - DELAYED – Will not be complete until July – September. Spine is progressing but slowly working with TM clearing blockages.

Navenby 4 – System updates complete, BT carrying out final checks to ensure service availability; cabinet is expected to be accepting orders next week.

Normanby By Spital 2 – Power outstanding but prioritised for delivery before the end of June.

Sibsey 1- Dslam programmed to be stood 27/5.

South Rauceby 1 – New power quote received and authorised, in the plan for power to be connected next week.

Spalding 50 –Still waiting details from Power company due deep excavations on power.

Sudbrooke Park 18 – Shifted slightly in the plan - due to be completed before June 2015, requires overlay

Sutterton 3 – Now complete, should be accepting orders within the next 2 weeks.

 

April 2015

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide