Project Update - Week Ending 23rd January 2015

23rd January 2015

Phasing 4-5

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Since the last update another 2 cabinet have been enabled.

 

Cabinet 35 on the SKEGNESS exchange

Cabinet 1 on the WAINFLEET exchange

 

Cabinet progress update

Ancaster 2 –Traffic Management is still underway

Ancaster 3 – Traffic Management is still underway

Ancaster 4 - Traffic Management is still underway

Billinghay 1 – Awaiting update

Billinghay 6 – This cabinet is still forecasted for mid February

Birchwood 45 COMMERCIAL CABINET – Planning works under way – works not expected to take long once this has been started

Birchwood 74 COMMERCIAL CABINET –on site cabling should be completed end of next week

Butterwick 3 – Management will urge for completion  as soon as possible

Cranwell 4 – Traffic management issues are still ongoing – this is being affected by the Ancaster cabinet Traffic management issues.

Culverthorpe 1 & 2 - Further multiple blockages near gas main requires joint visit with utilities – this will be underway soon

Donington 6 – Cabinet is due to be stood in the coming week -  further jointing works will then be completed before the cabinet goes 'ready for service'

Friskney cabs x 4 – Blockage clearance underway. Two cabinets have been stood – the others are expected to be stood in the near future.

Grantham 81 – Cabinet is due to be stood in position in February

Horncastle 3 – Overlay cables now required for powering up the cabinet – this is in hand

Heckington 1 –This was 'ready for service' 13th January, the cabinet will be able to have products brought from it (approximately) within the next week

Normanby by Spital EO Lines - New ducting is now in place, and the cabinet requires cabling and connecting to power – this is ongoing

South Rauceby 1 –Traffic management required due to railway line. Applications are being processed by Network Rail.

South Rauceby 2 –  cabinet stood and powered, due for electronic meter certificate checks on the  26th January.

Spalding 50 –Due for deployment in March

Spalford 1 – New duct routing has come across power supply so re-routing has been carried out.

Welton EO lines – Welton 1 build is complete – waiting for systems to be updated. Welton 9 ongoing – blockages found

Withern Cabs x 2 – Still on track for completion on 7th February 2015

progress thermometer 090115

 

 

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide