Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here
CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.
Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice
Cabinet 1 on the BILLINGBOROUGH exchange
Cabinet 10 on the CAISTOR exchange
Cabinet 4 on the DOWSBY exchange
Cabinet 3 on the EAST KIRKBY exchange
Cabinet 4 on the FOLKINGHAM exchange
Cabinet 6 on the LONG BENNIGTON exchange
Cabinet 10 on the SCOTTER exchange
Cabinet 28 on the SLEAFORD exchange
Cabinet 1 on the WITHAM ON THE HILL exchange
If you have any queries please contact us
Delayed cabinets
Please note that we can only provide updates on delayed cabinets.
Bainton 4 – Cabinet being stood in position today. Booked in for power connection 28/10/15
Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December; new duct required over the bridge. 15/10/15 Bridge work to commence 12/11/15
Bassingham 4 - only requires power now, booked in for 10/11/15
Billinghay 6 - will be enabled next quarter, before the end of December
Birchwood 63- DELAYED – this cabinet will not be completed until October. BT cabling late August - ongoing
Buckminster 7 - Overlay works (on poles) required expected delivery in this quarter, before the end of September. DELAY - Delays in cabinet build due to agreement of Sunday working/road closure. Likely completion mid-October. Sundays works still required
Burgh on Bain 3 & 4 - Power wayleaves required. Ongoing discussions with landowner
Chapel St Leonards 12 – No change but BT are meeting with the Developer (Keir Homes) today
Cranwell 2 - This cab should be ready for service this quarter
Cranwell 5 – This cab should be ready for service this quarter
Gosberton 5 – Issues with bridge resolved - should be ready for service this quarter
Grantham 16 - SHIFTED - Expected delivery between October and December. Civils work commenced 09/10/2015
Grantham 21– Wayleave issue now resolved. Should be ready for service by the end of November
Grantham 34 – Chasing new date with power company for works under traffic management
Holbeach St Johns 1 - DELAYED - All poles erected at the weekend, waiting remedial civils work likely to be RFS October - November due to size of the PON
Huttoft 1 - works are currently in progress
Huttoft 3 - Fibre needs to be provided - estimated at the beginning of November
Kirton 5 (amalgamated with 13) - Should be RFS early October as big copper job (De-load / Re-load with cab 13)
Kirton 8 - engineers are working on this today
Langrick 1– Expected physical completion early November
Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015
Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015
Lincoln 133 - New duct to be installed to allow provision of Copper and Fibre. Work commencing late October
Long Sutton 4 - DSLAM needs moving
Metheringham 1 - Power connection date has had to be changed as a new source has been identified which required a road crossing - estimated for 12/11/15 Ready for service estimated late November
Metheringham 6 - Power connection date has been changed - now estimated for 12/11/15
Metherinham 14 - Digby - this is being planned and is in the system at present.
Old Leake 6 – Civils issues are ongoing - expected to be ready for service mid-December
Normanby By Spital 2 – DELAY - cabinet failed commissioning tests. With Huawei to resolve. Huawei at site 26/10/15
North Somercotes 3 - Cabinet has been moved to facilitate new development
South Cockerington 2 - overlay works in progress (over poles)
Spalding 50– Engineers are booking in the power connection with their contractors - Date to be agreed.
Spalding 16 & 26– DELAYED - Completion will probably be in November, new duct required
Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December
Spilsby 1- DELAYED - De-load / Re-load and road closure.
Spilsby 4 - Just needs power and certification. Working with power company to get dates for this. Estimated for delivery 14/11/15
Swaton 2 & 3 - . HA originally rejected location for Swaton 3; we now have agreement on location. Estimated cab stand date 12/11/15
Swinderby 1 - Planner has released fibres BT can use - expected ready for service mid-December
Torksey 3 - Job in progress, waiting for gas board Western Power meeting before work can be completed
Wickenby 2 – Road crossing complete, chasing connection date with power company
Withern 1- Cabinet is stood, overlay for copper and light programmed in for this week. Estimation to be powered 22/10/15
Witham on the Hill 2 - should be RFS approximately 06/11/15
To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide
Enter your postcode in the box to find out how the Onlincolnshire campaign is making a difference to your community...
Test the speed of your broadband with the broadband speed checker