Project Update - Week ending 23rd October 2015

23rd October 2015

 

Phasing datesPhasing 7

 Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet  1 on the  BILLINGBOROUGH exchange

Cabinet  10 on the CAISTOR exchange

Cabinet  4 on the DOWSBY exchange

Cabinet  3 on the EAST KIRKBY exchange

Cabinet 4 on the FOLKINGHAM exchange

Cabinet  6 on the LONG BENNIGTON exchange

Cabinet 10 on the SCOTTER exchange

Cabinet 28 on the SLEAFORD exchange

Cabinet 1 on the WITHAM ON THE HILL exchange


If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

 

Bainton 4 – Cabinet being stood in position today. Booked in for power connection 28/10/15


Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December; new duct required over the bridge. 15/10/15 Bridge work to commence 12/11/15


Bassingham 4 - only requires power now, booked in for 10/11/15

Billinghay 6 - will be enabled next quarter, before the end of December


Birchwood 63- DELAYED – this cabinet will not be completed until October. BT cabling late August - ongoing


Buckminster 7 - Overlay works (on poles) required expected delivery in this quarter, before the end of September. DELAY - Delays in cabinet build due to agreement of Sunday working/road closure. Likely completion mid-October. Sundays works still required


Burgh on Bain 3 & 4 - Power wayleaves required. Ongoing discussions with landowner


Chapel St Leonards 12 – No change but BT are meeting with the Developer (Keir Homes) today


Cranwell 2 - This cab should be ready for service this quarter


Cranwell 5 – This cab should be ready for service this quarter


Gosberton 5 – Issues with bridge resolved - should be ready for service this quarter


Grantham 16 - SHIFTED - Expected delivery between October and December. Civils work commenced 09/10/2015


Grantham 21– Wayleave issue now resolved. Should be ready for service by the end of November


Grantham 34 – Chasing new date with power company for works under traffic management


Holbeach St Johns 1 - DELAYED - All poles erected at the weekend, waiting remedial civils work likely to be RFS October - November due to size of the PON


Huttoft 1 - works are currently in progress


Huttoft 3 - Fibre needs to be provided - estimated at the beginning of November


Kirton 5 (amalgamated with 13) - Should be RFS early October as big copper job (De-load / Re-load with cab 13)


Kirton 8 - engineers are working on this today


Langrick 1– Expected physical completion early November


Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015


Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015


Lincoln 133 - New duct to be installed to allow provision of Copper and Fibre. Work commencing late October


Long Sutton 4 - DSLAM needs moving


Metheringham 1 - Power connection date has had to be changed as a new source has been identified which required a road crossing - estimated for 12/11/15 Ready for service estimated late November


Metheringham 6 - Power connection date has been changed - now estimated for 12/11/15


Metherinham 14 - Digby - this is being planned and is in the system at present.


Old Leake 6 – Civils issues are ongoing - expected to be ready for service mid-December


Normanby By Spital 2 – DELAY - cabinet failed commissioning tests. With Huawei to resolve. Huawei at site 26/10/15


North Somercotes 3 - Cabinet has been moved to facilitate new development


South Cockerington 2 - overlay works in progress (over poles)


Spalding 50– Engineers are booking in the power connection with their contractors - Date to be agreed.


Spalding 16 & 26– DELAYED - Completion will probably be in November, new duct required


Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December


Spilsby 1- DELAYED - De-load / Re-load and road closure.


Spilsby 4 - Just needs power and certification. Working with power company to get dates for this. Estimated for delivery 14/11/15


Swaton 2 & 3 - . HA originally rejected location for Swaton 3; we now have agreement on location. Estimated cab stand date 12/11/15


Swinderby 1 - Planner has released fibres BT can use - expected ready for service mid-December

 

Torksey 3 - Job in progress, waiting for gas board Western Power meeting before work can be completed


Wickenby 2 – Road crossing complete, chasing connection date with power company


Withern 1- Cabinet is stood, overlay for copper and light programmed in for this week. Estimation to be powered 22/10/15


Witham on the Hill 2 - should be RFS approximately 06/11/15

October process

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide