Project Updates

Project Update - Week ending 24th April 2015

24th April 2015

 

Phasing datesPhasing 4-5

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Completed cabinet list

Cabinet 4 on the BURGH exchange

Cabinet 602 on the FENTON CLAYPOLE exchange

Cabinet 39 on the GRANTHAM

Cabinet 7 on the SUTTON BRIDGE exchange

Cabinet 1 on the SWABY exchange

 

Please note that we can only provide updates on delayed cabinets.

If you have any queries please contact us

 

Delayed cabinets

Billingborough 1 , 3  & 5 amalgamation – 1 & 5 are still on target for mid-May

Billinghay 1 – DELAY – 844m of fibre remaining. Traffic management booked 30th April.

Culverthorpe – Culverthorpe 1 will be 'lit' next week – after commissioning this will be ready for service. Two weeks after being ready for service it will be ready for orders. Culverthorpe 2 will be stood in position as a priority. Due to be completed before the end of June.

Gosberton 5 –Duct damaged over bridge. Will need replacing as digs unsuccessful. Liaison with Rail company ongoing

Grantham 21 – Power connection needs completing

Holbeach St Johns 1 - Shifted in the plan. Now to be enabled July - September 2015

Horncastle 3 –New duct job issued and prioritised

Kirton 5 - work is with the engineers and is still pending

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Old Leake 3 – Extensive traffic management and civil engineering required, work on-going.

Old Leake 6 -  Extensive traffic management and civil engineering required, work on-going.

Normanby By Spital 2 – Power outstanding but prioritised for delivery before the end of June.

Sibsey 1-  Delivery of completed cabinet expected in June.

South Rauceby 1 -. Power planned for connection 30th April

Spalding 50 –BT is on track with current deployment

Sudbrooke Park 18 – Shifted slightly in the plan - due to be completed before June 2015

Sutterton 3 – Power connection has been requested.

Tetford 2 – Due for deployment early June

Navenby 4 – Ready for Service. In two weeks products can be ordered from this cabinet.

 

April 2015

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide