Project Update - Week ending 24th July 2015

24th July 2015

Phasing datesPhasing 6-7

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible

 

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet 13 on the BOURNE exchange

Cabinet 2 on the MAREHAM LE FEN exchange

Cabinet 2 on the TETFORD exchange

Cabinet E3 on the TORKSEY exchange

 

Please note that we can only provide updates on delayed cabinets.

 

If you have any queries please contact us

 

Delayed cabinets

 

Ancaster 4 – Natural England now given Ok to   start. Traffic management applied for to start works. 5.4Km of network to   cable. 05/06/15 No Change – awaiting traffic management permission. 12/06/15   Cabling has been started and is ongoing 03/07/15 Cabling is ongoing 10/07/15   Cabling ongoing 4K  completed 1.5K left 17/07/15 - still ongoing   24/07/15 remaining cabling is progressing slowly alongside traffic management

Bainton 4 –Currently with planners, BT will   push for early completion 05/06/15 BT are chasing planners for progression   12/06/15 Still with planning team 03/07/15 No change in situation 17/07/15 No change, BT chasing planning for a resolution 24/07/15 No change

Bardney 6 – DELAYED – this cabinet will not be   completed until quarter of October – December 10/07/15 Meeting held again   this week Ref New Duct over bridge Oct - Dec still completion period 24/07/15 road closure required for duct over bridge. No change.

Billingborough 1 - Cabinet 1 has some planning   delays associated and BT are moving to resolve as soon as possible. We will   update within the next week or so on progress. 10/07/15 Planning issues are   still being dealt with. We are hoping to have timescales for this in the   coming weeks 17/07/15 - still awaiting timescales 24/07/15 No change

Billingborough 5 – currently taking orders but   we are aware of issues associated with this cabinet and Billingborough 5 and   are trying to remedy these as soon as possible 17/07/15 No change 24/07/15 No change

Birchwood 38 - New duct laid and blown fibre   tubing provided. Cab stand with contractor. Will urge for completion early   July. 10/07/15 Cabinet will be stood between now and the 18th July   17/07/15 Looking ready for infrastucture completion in four weeks 24/07/2015 only awaiting certificate. Should be ready for service within a week. Approx. two weeks after this, products can be ordered from it.

Birchwood 63 - DELAYED – this cabinet will not   be completed until quarter of October - December 24/07/15 no change. Cabling started but expected completion as per previous.

Birchwood 72 - Just needs copper and Light -   should be completed before the end of this month. 10/07/15 Cabinet has a land   wayleave issue but the entire network is proven. 17/07/15 No change 24/07/15 No change

Bottesford 5 – Should be completed by the end   of the month. Just needs fibre linking up to it. 10/07/15 Looking to connect   fibre this Sunday 17/07/15 Infrastructure is complete. Should be able to accept orders in approx. 2 weeks 24/07/15 - awaiting commisioning

Buckminster 7 - Road crossing was completed at   the weekend and now working on cabling 17/07/15 Sunday required for stand up   of cabinet. Expected delivery in this quarter, before the end of September  24/07/15 No change

Chapel St Leonards 12 – Shifted in plan. Now   expected to be excepting orders in August, 10/07/15 – no change 17/07/15 Wayleave outstanding with developer.  24/07/15 No change

Corby Glen 1 & 2 – Traffic management   authorisation has caused these to be delayed. Set to be delivered this   quarter, before the end of September.   10/07/15 Traffic management   issues remain. Trying to rectify 17/07/15 A1+ insist on 3 month notice for blockages either side of A1. Expected delivery this quarter.  24/07/15   No change

Cranwell 2 - Delays linked to Ministry of   Defence property and survey for Dslam now complete and with planning.   10/07/15 No change 24/07/15 wayleave required for new DSLAM cabinet. Contact made with MOD and discussions are due next week

Cranwell 5 – No longer shifted to August   -  this cabinet should be enabled before the end of the month as now   only needs fibre connecting to it. 10/07/15 POSSIBLE DELAY The structure may   need to be moved. 17/07/15 No change 24/07/15 second survey completed Tuesday. Awaiting formal survey return.

Folkingham 1 – this cabinet should be enabled   before the end of the month 10/07/15 No change 17/07/15 2 additional   blockages to be cleared, cabinet expected to be live mid August. 24/07/15 No change

Folkingham 3 – shifted slightly in plan due to   delays. Should be enabled before the end of September 10/07/15 No change 17/07/15 no change  24/07/15 No change

Fulbeck 3 – this cabinet should be enabled   before the end of the month. Just needs fibre feeding to it. 10/07/15 Still   Aiming for end of Month. Cabling and trenching ongoing 17/07/15 no change   23/07/15 fully cabled. Should be RFS by end of month/first week Aug (Services should be available beginning of August)

Gosberton 5 – BT have agreed a method for   spanning the bridge and are waiting for details of this work before it can be   included in the engineers work stack. 05/06/15 No change 12/06/15 – overlay   works have been issued to engineers. 03/07/15 ongoing 10/07/15 Ongoing Will has asked for meeting with highways and Bridge people to try and move it forward work still with Network Rail. 17/07/15 Chasing for meeting to agree way forward.23/07/15 Network Rail engineer on leave. Will chase again next week.

Grantham 16 SHIFTED- New duct on Road Crossing   requiring a road closure. Engineers are still waiting for dates for when this can be completed. 10/07/15 No Change 17/07/15 SHIFTED - Expected delievery between October and December 2015 24/07/15 No change

Grantham 21– Just needs power and Light -   completion July 17/07/15 Power wayleave still required - chasing with power company 24/07/15 No change

Grantham 34 – 500mts power which will delay   enablement until July according to Western Power. 12/06/15 No change 03/07/15   works are with Western Power 10/07/15 No Change 17/07/15 chasing new date   with power company for works under traffic management 23/07/15 Still awaiting date

Holbeach St Johns 1 - DELAYED – Will not be   complete until July – September 10/07/15 No Change 17/07/2015 - no change 24/07/15 No change

Honington 1 – power provision ongoing – long   route which has meant delays. 10/07/15 Power connection date 15th Aug 24/07/15 No change

Honington 603 – this cabinet should be enabled   by the end of the month. Currently awaiting power connection and   certification. 10/07/15 Power connection was booked in for yesterday 17/07/2015 - Power certification failed, secondary earth rod required, now expected live end August. 24/07/15 Ready for service - should be excepting orders in two weeks from now

Horsington R1 – Ready for Service. Should be accepting orders in the coming weeks. 24/07/15 No change

Kirton 5 (amalgamated with 13) - work is with the engineers and is still pending. 05/06/15 No change 12/06/15 Awaiting overlay  works for copper cable 03/07/15 ongoing 10/07/15 Still Waiting Duct work to   Link these 24/07/15 No change

Knipton 1 & 3 – these cabinets should be   enabled by the end of the month. 10/07/15 Duct works continuing at present   17/07/15 no change 24/07/15 one DSLAM still to build. Likely delivery now   mid-August.

Langrick 1– DELAY linked to new duct over bridge   which requires various meeting with Bridge engineers and Contractors.   10/07/15 Meeting held this week to try and progress duct over Bridge 17/07/15   Meeting held and awaiting programme data from supplier  24/07/15 No change

Langrick 2 – this cabinet should be enabled by   the end of the month  24/07/15 No change

Lincoln 76 SHIFTED- this cabinet should be enabled   by the end of the month. DELAYED - Now expected late quarter 3, November - December 2015

Lincoln 132 SHIFTED – Shifted in   the plan - due for deployment July – September 2015DELAYED - Now expected late quarter 3, November - December 2015

Lincoln 133 - New duct required between   existing cabinet and new cabinet 03/07/15 - ongoing 10/07/15 Waiting for job   to come through from planning to deal with copper ties 17/07/15 - delivery expected before the end of September. 24/07/15 No change

Old Leake 1, 3, 4, 5, 6 – DELAYED – Will not   be complete until July – September. Spine work is progressing but slowly   working with traffic management clearing blockages. 10/07/15 Still   progressing with blockage clearance. Old Leake 5 will be considerably delayed   as a road closure required for this which requires 13 week notice. 17/07/15   Cabinet 1,3 and 4 expected this quarter, before the end of September. Cabinet   5 requires road closure and 6 has extensive overlay requirements. 24/07/15 No change

Normanby By Spital 2 – High cost power - quote   approved; with WPD 10/07/2015 Just waiting power 24/07/15 No change - delivery expected before the end of September

Sleaford 28 - Looking to use an existing fibre   to expedite delivery. This cabinet should be completed by the end of this quarter, before the end of September. 10/07/15 No Change 17/07/15 no change. 24/07/15 No change

Spalding 50– Shuttering complete. With WPD to resource. End june / early July 10/07/15 No Change 17/07/15 Pushing for power this quarter.  24/07/15 No change

Spalding 16 & 26– DELAYED. Should be completed   by the end of this quarter, before the end of September 10/07/15 No Change 17/07/2015 no change FURTHER DELAY - Completion will probably be in November

Spalding 45 – DELAYED. Will be   completed towards the end of this quarter, around September time. 10/07/15   one section of Duct overlay (overhead wiring) required 17/07/15 New position   agreed to avoid wayleave - now likely to be delivered between October and December 24/07/15 No change

Spilsby 1- only requires copper and fibre feeding   to it now. Should be completed soon. 10/07/15 The cabinet may need to be   moved - meeting with highways 17/07/15 SHIFTED Now will not be completed October - December as cabinet needs to be rebuilt.  24/07/15 No change

Sudbrooke Park 18 – Direct labour engineers on   with now, expected delievery 1st week of July 10/07/2015 Cabling delayed on final section linked to TM  24/07/15 No change

Whaplode Drove 5 - 24/07/15 ready for service. Should be availalble to take orders within two weeks

Wickenby 2 – works are currently progressing   to feed fibre to new structure. 10/07/15 The cabinet is due to be stood between the 14th and 24th June. All ducting   has been proved. 88m of fibre remaining to be jointed. 17/07/15 Expected   delivery this quarter, should be able to order services before September 2015  24/07/15 No change

Withern 1,3 & 4 - these cabinet should be   enabled by the end of the month 10/07/15 Still on target but one cabinet is waiting a duct overlay (overhead wiring) section. no change  24/07/15 No change

 

 progress july

 

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide