Project Update - Week ending 24th June 2016

24th June 2016

Contract two planning phase

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in time. BT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

Structure V2 on the Heckington exchange

Structure V4 on the Heckington exchange

Cabinet 5 on the Kirton exchange

Cabinet 50 on the Lincoln exchange

Structure V2 on the Moulton exchange

Cabinet 2 on the Old Leake exchange

Cabinet 34 on the Skegness exchange

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Delayed cabinets

Dowsby 602 - With commisioning team, on way to being fully commisioned.

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit and there is more planning associated with doing this.

Gosberton 5 – Still with Network Rail

Holbeach St Johns 1 - Timescales shifted - Moleploughing still ongoing at this time

Metheringham 3/2 (Nocton) -This has now had the new fibre Cabinet shell resighted across from the post office. Copper rearrangement works is being planning to shift all the copper pairs from old cab to new PCP 17

Metheringham 3/1 (Dunston) -  Undergoing commisioning

Spalding 16 – Discussions ongoing with property owner

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide