Phasing datesPhasing 6-7

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependent upon demand. We are pushing BT to clear these issues as a matter of urgency, conscious that some cabinets are unavailable for an unacceptably long period. Please bear with us and additional capacity will be added as soon as possible

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet  4 on the  ANCASTER exchange

Cabinet  2 on the BASSINGHAM exchange

Cabinet  8 on the BILLINGBOROUGH exchange

Cabinet  15 on the GAINSBOROUGH exchange

Cabinet  14 on the LONG SUTTON exchange

Cabinet  3 on the MARSHCHAPEL exchange

Cabinet  8 on the MOULTON exchange

Cabinet  5 on the OLD LEAKE exchange

Cabinet  1 on the OLD LEAKE exchange

Cabinet  2 on the OWERSBY MOOR exchange

Cabinet  2 on the SEARBY exchange

Cabinet  3 on the SWINDERBY exchange

Cabinet  4 on the SWINDERBY exchange

Cabinet  5 on the SWINDERBY exchange

Cabinet  3 on the TEALBY exchange

 

If you have any queries please contact us

 

Phase 6

UPDATE 21/08/15 Swinderby 6 - should be 'ready for service' 30th September. Approx two weeks after this services should be available from this cabinet.

Swinderby   1 - Cable recovery teams working to try to save the need to put in 3km of new duct

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

Bainton   4 – Position agreed by Highways Authority and Town planners have agreed to   early start on this. Processes being expedited to make sure it gets to RFS   ASAP
Bardney   6 – DELAYED – this cabinet will not be completed until quarter of October –   December; new duct required over the bridge
Billinghay   6 - will be enabled next quarter, before the end of December
Billingborough   1 - Will be RFS w/e 30th Sept. Two weeks after this services can be ordered from this cabinet.
Billingborough   5 – Will be made live to Internet Service Providers once Billingborough 1 has   gone live
Birchwood   63 - DELAYED – this cabinet will not be completed until quarter of October.   BT cabling late August (half completed)
Buckminster   7 - Overlay works (on poles) required expected delivery in this quarter,   before the end of September. DELAY - Delays in cabinet build due to agreement   of Sunday working/road closure. Likely completion mid-October
Chapel   St Leonards 12 – Shifted in plan. Wayleave still outstanding with developer
Cranwell   2 -  This cab is planned and job has   been designated to the engineers to stand. Cabinet stand and completion is   forecast for next quarter
Cranwell   5 – Second survey completed, awaiting formal survey return. Delivery forecast   for next quarter
Folkingham   3 – Due to be RFS 30th September
Gosberton   5 – Overlay required over the bridge, Next quarter delivery
Grantham   16 - SHIFTED - Expected delivery between October and December
Grantham   21– Power position not agreed with WPD. Site meeting next week
Grantham   34 – Chasing new date with power company for works under traffic management -   chasing today 04/09/15
Holbeach   St Johns 1 - DELAYED - All poles erected at the weekend, waiting remedial   civils work likely to be RFS October - November due to size of the PON
Honington   1 – Ready for service - in less than two weeks products can be ordered from   this cabinet
Kirton 5   (amalgamated with 13) - Should be RFS early October as big copper job   (De-load / Re-load with cab 13)
Knipton   1 & 3 – Ready for service - in two weeks products can be ordered from   these cabinets
Langrick   1– DELAY linked to new duct over bridge which requires various meeting with   Bridge engineers and Contractors. 1KM of duct work to go over a deep dyke. In   progress
Langrick   2 – power connection date will be 23/09/15 This will be Ready For Service   Shortly. In approximatly two weeks products can be ordered  from this cabinet
Lincoln   76 SHIFTED - Now expected late quarter 3, November - December 2015
Lincoln   132 SHIFTED – Now expected late quarter 3, November - December 2015
Lincoln   133 - Cab up and powered, needs copper and fibre, but new duct required which   could cause further delay
Metheringham   1 Due to be supplied with power 12th October - (Digby, Roughton?)
Metheringham   6 - Cabinet stood in position. With planners to provide route utilising   existing fibre 11/09/15 Due to be supplied with power 12th October
Old   Leake 1, 5, 6 –  1 & 5 are at RFS. Civils   for 6 ongoing
Normanby   By Spital 2 – High cost power - quote approved; Power wayleaves required -   25/09/15 Meeting organised for today to resolve power wayleave issues
Sleaford   28 - Should be RFS w/e 30th Sept
Spalding   50– New point of connection point found; with the engineering team to be   programmed with Western power
Spalding   16 & 26– DELAYED - Completion will probably be in November, new duct   required
Spalding   45 – DELAYED. New position agreed to avoid wayleave - now likely to be   delivered between October and December
Spilsby   1- DELAYED - De-load / Re-load and road closure. Next quarter delivery
Swaton 2   & 3 - Next quarter delivery. HA originally rejected location for Swaton   3; we now have agreement on location.
Swinderby   1 - Cable recovery teams working to try to save the need to put in 3km of new   duct
Swinderby   6 - due RFS 30/09/15
Wickenby   2 – Road crossing for power. 22/10/15
Withern   1- Still chasing power wayleaves with NPG 25/09/15 Meeting organised for   today to resolve power wayleave issues
Witham   on the Hill 1 & 2 Witham 1 will be RFS next week. Witham 2 requires a   cabinet stand date 25/09/15 - no change

Progress September

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide