Project Update - Week ending 26th February 2016

26th February 2016

Phasing datesphasing 8

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in time. BT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Cabinet 15 on the Metheringham exchange

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Delayed cabinets

Burgh on Bain 4 - Power connection re-booked for 16/03/16

Cranwell 2 - Ready for service - products will be available from this cabinet within 2 weeks

Corby Glen 5 – Power connection booked 01/03/16; estimated completion date TBC

Dowsby 5 - power booked for 11/04/16 but engineers are looking to bring this forwards; estimated completion date 31/03/16

Dowsby 602 - Estimated completion date 31/03/16

Fulbeck 606 - Estimated completion date 31/03/16

Gosberton 5 – Estimated completion date 31/03/16

Grantham 16 - Due to difficulty in completing civils activity in advance of cab shift. This has become more delayed - estimated completion 16/03/16

Grantham 34 – Power connection booked 29/02/16

Greatford 8 - Ready for service - products will be available from this cabinet within 2 weeks

Holbeach St Johns 1 - Estimated completion date 31/03/16

Huttoft 1 - Further delay due to water pipe damage in vacinity of planned civils; estimated completion date 02/03/16

Huttoft 3 - Further delay due to water pipe damage in vacinity of planned civils; estimated completion date 02/03/16

Kirton 5 - Highways issues with civils work - expected completion date 09/03/16

Kirton 8 - Highways issues with civils work - expected completion date 09/03/16

Lincoln 50 - Lane closure agreed with Lincs Highways Authority. Expected completion 28/02/16

Lincoln 76 - Ready for service - products will be available from this cabinet within 2 weeks

Lincoln 132 – Estimated completion date 16/03/16

Metheringham 1 - Traffic management re-booked estimated completion date shifted 09/03/16

Metheringham 3/2 (Nocton) - Estimated completion 31/03/16

Metherinham 14 - Ready for service - products will be available from this cabinet within 2 weeks

North Somercotes 3 - Estimated completion date 02/03/16

Owersby Moor E4 - On hold pending decision relating to high costs

Normanby By Spital 2 – Estimation for build completion the end of Feb - products should be available early March

Spalding 16 – Estimated completion 10/03/16 due to additional blockages

Withern 1 - Power agreed and booked. Estimated build completion mid-March

 

progress feb

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide