Project Update - Week ending 27th November 2015

27th November 2015

Phasing datesPhasing 7

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

No additional cabinets have gone live this week

If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

Bainton 4 – new duct job with contractor. ECD early/mid-December

Bassingham 4 - Power connection on BT land. Property manager to agree. ECD 16/12

Billinghay 6 - KEIR Homes have signed the wayleave - To be programmed. ECD 16/12

Birchwood 63 - Estimated completion date 9/12

Buckminster 7 - Ready for service - products should be available in the coming weeks

Burgh on Bain 3 & 4 - Estimated completion date 16/12

Chapel St Leonards 12 – Estimated completion date 16/12

Cranwell 2 - Estimated completion date 16/12 - ECD date moved due to RAF permission to site DSLAM - ongoing negotiations

Cranwell 5 – Estimated completion date 2/12

Fulbeck 606 - Under review due to engineering difficulties and associated excessive costs

Gosberton 5 – Estimated completion date 9/12

Grantham 16 - ECD early January due to difficulty in completing civils activity in advance of cab shift.

Grantham 21– Estimated completion date now 2/12 due to WPD resource shortage

Grantham 34 – Estimated completion date 9/12

Holbeach St Johns 1 - Expected January due to additional civils issues.

Huttoft 1 - Estimated completion date 16/12

Huttoft 3 - Estimated completion date 16/12

Kirton 5 - Expected January due to additional civils issues.

Kirton 8 - Estimated completion date 16/12

Lincoln 76 - Estimated completion date 9/12

Lincoln 132 – Estimated completion date 9/12

Lincoln 133 - New duct required to be laid - estimated completion date still 16/12

Long Sutton 4 - Estimated completion date 9/12

Metheringham 1 - Estimated completion date 9/12

Metheringham 6 - Estimated completion date 2/12

Metherinham 14 - Estimated completion date 9/12

Old Leake 6 – ECD 23/12 - ECD moved due to extra overlay required that was missed by contractor.

Normanby By Spital 2 – Estimated completion date 9/12

North Somercotes 3 - Cabinet has been moved to facilitate new development. Estimated completion date 23/12

South Cockerington 2 - Estimated completion date 16/12

South Cockerington 3 - Estimated completion date 16/12

Spalding 50– ECD 9/12. Joint visit with WPD to see if new Point Of Connection (POC) can be found so Nno need for deep excavation shuttering

Spalding 16– Estimated completion date 2/12

Spalding 26– Estimated completion date 2/12

Spalding 45 – Estimated completion date 2/12

Spilsby 1 - Estimated completion date 16/12

Swaton 2 - With commissioners

Swaton 3 - Estimated completion date 9/12

Swinderby 1 - Estimated completion date 25/11

Tetford EO (3) DELAY - issue has arisen in ductwork; estimated completion date 16/12

Withern 1- Land ownership change has caused dispute over wayleave for pole. WPD to seek alternatives.

Witham on the Hill 2 - Ready for service - products should be available in the coming weeks

 

November Progress

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide