Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here
CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible
Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice
Cabinet 1 on the BISHOP NORTON exchange
Cabinet 3 on the NORTH THORESBY exchange
Please note that we can only provide updates on delayed cabinets.
If you have any queries please contact us
Delayed cabinets
Ancaster 4 – Ready for service - products should be available to order from this cabinet next week |
Bainton 4 – Position agreed by Highways Authority and Town planners have agreed to early start on this. Processes being expedited to make sure it gets to RFS ASAP |
Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December; new duct required over the bridge |
Billingborough 1 - Cab site surveyed, location agreed with Highways Authority; with Contractors to stand and then we will joint, expected late this quarter / early next |
Billingborough 5 – Cab site surveyed, location agreed with Highways Authority; with Contractors to stand and then we will joint, expected late this quarter / early next |
Birchwood 63 - DELAYED – this cabinet will not be completed until quarter of October. BT cabling late August (half completed) |
Birchwood 72 - RFS - internet services providers should be offering services in 2 weeks time |
Buckminster 7 - Overlay works (on poles) required expected delivery in this quarter, before the end of September. |
Chapel St Leonards 12 – Shifted in plan. Wayleave still outstanding with developer |
Corby Glen 1 & 2 – Traffic management authorisation has caused these to be delayed A1+ will not let BT in to clear blockages & cable until the 7th September, should be available mid September |
Cranwell 2 - This cab is planned and job has been designated to the engineers to stand |
Cranwell 5 – Second survey completed, awaiting formal survey return |
Folkingham 1 – Fibre damaged by an other. BT fibre jointers are working on this today |
Folkingham 3 – Fibre damaged by an other. BT fibre jointers are working on this today |
Fulbeck 3 – RFS - internet services providers should be offering services in 2 weeks time |
Gosberton 5 – Chasing Network Rail for a meeting to agree way forward |
Grantham 16 - SHIFTED - Expected delivery between October and December |
Grantham 21– Power wayleave still required, chasing with power company |
Grantham 34 – Chasing new date with power company for works under traffic management |
Holbeach St Johns 1 - DELAYED - All poles erected at the weekend, waiting remedail civils work likely to be RFS October - November due to size of the PON |
Honington 1 – Power provision ongoing – long route which has meant delays. Waiting on WPD for a connection date |
Kirton 5 (amalgamated with 13) - Should be RFS early October as big copper job (De-load / Re-load with cab 13) |
Knipton 1 & 3 – Outstanding civils - Expected to be clared by End of August |
Langrick 1– DELAY linked to new duct over bridge which requires various meeting with Bridge engineers and Contractors. 1KM of duct work to go over a deep dyke. In progress |
Langrick 2 – Awaiting power connection date |
Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015 |
Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015 |
Lincoln 133 - Cab up and powered, needs copper and fibre, but new duct required which could cause further delay |
Old Leake 1, 3, 4, 5, 6 – DELAYED – cabinets 1,3,4 and 5 should be ready for service at the end of September. Two weeks after this services can be ordered. Cab 6 will be delayed further as a new duct needs to be installed |
Normanby By Spital 2 – High cost power - quote approved; Power wayleaves required |
Sleaford 28 - Looking to use an existing fibre to expedite delivery. This cabinet should be completed by the end of this quarter, before the end of September |
Spalding 50– New point of connection point found; with our civils team to be programmed with Western power |
Spalding 16 & 26– DELAYED - Completion will probably be in November, new duct required |
Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December |
Spilsby 1- DELAYED - De-load / Re-load and road closure. Next quarter delivery |
Sudbrooke Park 18 – RFS - internet services providers should be offering services in 2 weeks time |
Swaton 2 & 3 Location for cabinet 3 has been rejected so planning works for this are ongoing. Cabinet 2 has a duct blockage which needs to be cleared hoping to have both up and live by end of the quarter |
Wickenby 2 – cabinet is up and cabled ready for jointing and power |
Withern 1 & 4 - Withern 1 waiting for engineering works; Withern 4 RFS |
Witham on the Hill 1 & 2 New duct is required |
To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide
Enter your postcode in the box to find out how the Onlincolnshire campaign is making a difference to your community...
Test the speed of your broadband with the broadband speed checker