Project Update - Week ending 29th April 2016

29th April 2016

Phasing datesphasing 8

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in time. BT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

There have been no additional cabinets enabled this week.

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice


Delayed cabinets

Burgh on Bain 4 - This is going to suffer significant delays - powerwork now underway

Dowsby 602 - Shifted again - Issue with steel duct is causing further delay. Estimated completion mid-May

Fulbeck 606 - Planning delay due to requirement to re-site the PCP. Delivery expected mid-May

Gosberton 5 – Site meeting being arranged to agree Pole positioning with Network Rail

Holbeach St Johns 1 - Moleploughing required on new planned route. ECD Late May

Kirton 5 - Build complete, products will be available from this cabinet within 2 weeks

Kirton 8 - Apologies recieved from BT due to an incorrect update. This build is not complete, but is expected to be in early May

Lincoln 50 - Late April estimation. New duct required.

Metheringham 3/2 (Nocton) - Cabinet is stood and powered. Estimated completion early May

Metheringham 3/1 (Dunston) - Cabinet stood, powered and coppered. Estimated completion early May

Owersby Moor E4 - This cabinet has been removed from the project because of excessive build costs. There is a requirement for a directional drill to be completed and this alone would cost over £150K and on that basis, we cannot justify this level of expenditure. We will of course continue to seek alternative technological solutions for this area

Spalding 16 – Early May estimate completion date. New underground chamber required

Progress April 2016

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide