Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here
CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.
Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice
Cabinet 4 on the Bainton exchange
Cabinet 3 on the Burgh on Bain exchange
Cabinet 5 on the Crowland exchange
Cabinet 84 on the Lincoln exchange
Cabinet 2 on the South Cockerington exchange
Cabinet 6 on the South Cockerington exchange
Cabinet 1 on the Tongue End exchange
We cannot currently access any emails. Please email us and we will get back to you as soon as we possibly can
If you have any queries please contact us
Delayed cabinet
Bassingham 4 – estimated completion date 03/02/16– now powered
Billinghay 6 – Products should be available from this cabinet within two weeks – ‘ready for service’ cabinet physically complete
Burgh on Bain 4 - Power connection booked 29/01/16
Cranwell 2 - Awaiting return of power wayleave; then 2 weeks’ notice required for clearance to site. Estimated completion 10/02/16
Corby Glen 5 – Estimated completion end of February / beginning of March
Fulbeck 606 - Will be added back in programme following review.
Gosberton 5 – Contact has been made with National Rail. Requires road closure once plans are agreed
Grantham 16 - Due to difficulty in completing civils activity in advance of cab shift. This has become more delayed - estimated completion mid-February
Grantham 34 – Shifted - estimated mid-February
Greatford 5 - delayed as duct damaged during roadworks. Expected delivery for February
Holbeach St Johns 1 - Expected mid-February due to additional civils issues.
Huttoft 1 - Estimated completion date shifted – delayed to 17/02/16
Huttoft 3 - Estimated completion date shifted - delayed to 17/02/16
Kirton 5 - Shifted - expected end of February.
Kirton 8 - Shifted - expected end of February.
Lincoln 50 - Lane closure agreed with Lincs Highways Authority. Expected completion 28/02/16
Lincoln 76 - Estimated completion date 25/02/16
Lincoln 132 – Estimated completion date 25/02/16
Lincoln 133 - Products should be available from this cabinet within two weeks – ‘ready for service’ cabinet physically complete
Louth 38 – estimated completion late March
Metheringham 1 - Traffic management resurveyed estimated completion date shifted 24/02/16
Metherinham 14 - PLEASE NOTE - there is a computer records issue here currently being resolved by an expert but there may be slight additional delay, 29/01/16 BT are still working on resolving this
Old Leake 6 – A blockage has been found but now cleared – estimated build complete 03/02/16
Owersby Moor E4 - duct issue under railway. Awaiting quote from contractor.
Normanby By Spital 2 – Issue with power pole, power connection booked 18/02/16
Spalding 16 – Estimated completion 12/02/16 due to additional blockages
Spilsby 1 - Date issue here, BT are chasing this to find out when products will be available.
Withern 1 - No change – alternative solution to power being sought
To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide
Enter your postcode in the box to find out how the Onlincolnshire campaign is making a difference to your community...
Test the speed of your broadband with the broadband speed checker