Project Update - Week ending 29th May 2015

29th May 2015

Phasing datesPhasing 5-6

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Completed cabinet list


Cabinet 1 on the BILLINGHAY exchange

Cabinet 1 on the FULBECK exchange

Cabinet 1 on the HORNCASTLE exchange

Cabinet 56 on the SPALDING exchange

Cabinet 3 on the SUTTERTON exchange

 

 

 

Please note that we can only provide updates on delayed cabinets.


If you have any queries please contact us

 

 

Delayed cabinets

Ancaster 4 – Natural England Now given Ok to start. Traffic management applied for to start works.  5.4Km of network to cable  

Bainton 4 –Currently with planners, BT will push for early completion

Billingborough 5 – 1 Blockage left but this needs 3 way lights required (applied for). 29/05/15 No change

Billingborough 3 – 1 Blockage left but this needs 3 way lights required (applied for). 29/05/15 No change

Birchwood 72 - Cabinet stood in position, works are ongoing to get this ready for service

Culverthorpe 2 – Ready for service. In approximately 2 weeks products can be ordered from this cabinet

Gosberton 5 – BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack. 29/05/15 No change

Grantham 21 – Power connection needs completing. Liaisons ongoing with the power company. 29/05/15 Traffic Management required for power road crossing, being organised.

Grantham 34 – 500mts power which will delay until July according to Western Power. 29/05/15 No change

Holbeach St Johns 1 - DELAYED – Will not be complete until July – September

Horncastle 3 – Duct work programmed/noticed this week, Power connection still required. 29/05/15 waiting for next possible date for power connection

Kirton 5 - work is with the engineers and is still pending

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Old Leake 3 – DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages

Old Leake 6 - DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages

Navenby 4 – System updates complete, BT carrying out final checks to ensure service availability; cabinet is expected to be accepting orders next week. 29/05/15 There are some issues with the computer systems which will drive these new products – waiting for conformation issues are dealt with

Normanby By Spital 2 – Power outstanding but prioritised for delivery before the end of June. 29/05/15 No change

Sibsey 1- Cabinet position has been agreed – this cabinet should be ready for service by the end of June, products will be available approximately 2 weeks after this.

South Rauceby 1 – New power quote received and authorised, in the plan for power to be connected next week. 29/05/15 Deep excavation is required. Shuttering to be provided by contractor for this.

Spalding 50 –Still waiting details from Power Company due deep excavations on power. 29/05/15 Deep excavation is required. Shuttering to be provided by contractor for this.

Sudbrooke Park 18 – Overlay is now complete, just needs the power to be certificated. Ongoing

 

progress May 2015

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide