Project Update - Week ending 2nd December 2016

2nd December 2016

Contract two phase one

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in timeBT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

Cabinet 7 on the Wainfleet exchange


Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Bourne 32 - Stood in position, coppered, powered and certificated. Waiting now for fibre to be installed but there is a road crossing to undertake first which Openreach are trying to organise

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit, replanning required, information on timescales wont be available until planning is complete

Gosberton 5 – Poling work complete, jointing to follow

Holbeach St Johns 1 - Moleplough ongoing. Build now to re-commence; ECD end of November

Metheringham 3/2 (Nocton) - Migration of lines from cabinet 3 to cabinet 17 is complete; services should be available imminently 

Spalding 16 – Land owner looking at wayleave agreements before work can commence

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide