Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here
CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependent upon demand. We are pushing BT to clear these issues as a matter of urgency, conscious that some cabinets are unavailable for an unacceptably long period. Please bear with us and additional capacity will be added as soon as possible
Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice
Cabinet 3 on the BASSINGHAM exchange
Cabinet 14 on the BOURNE exchange
Cabinet 1 on the FOSDYKE exchange
Cabinet 1 on the HONINGTON exchange
Cabinet 3 on the KNIPTON exchange
Cabinet 2 on the LANGRICK exchange
Cabinet 2 on the LAUGHTON exchange
Cabinet 1 on the NORTH SOMERCOTES exchange
Cabinet 3 on the SEARBY exchange
Cabinet 14 on the SPILSBY exchange
Cabinet 2 on the STENGIOT exchange
Cabinet 2 on the SWINDERBY exchange
Cabinet 6 on the SWINDERBY exchange
If you have any queries please contact us
Delayed cabinets
Please note that we can only provide updates on delayed cabinets.
Ancaster 6 - RFS. EO cabinet so may take longer than normal (i.e. 2 weeks) for products to be available
Bainton 4 – Due for standing in position today
Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December; new duct required over the bridge
Billinghay 6 - will be enabled next quarter, before the end of December
Billingborough 1 - Ready for service. In approx two weeks products can be ordered from this cabinet.
Billingborough 5 – Will be made live to Internet Service Providers once Billingborough 1 has gone live
Birchwood 63 - DELAYED – this cabinet will not be completed until quarter of October. BT cabling late August (half completed)
Buckminster 7 - Overlay works (on poles) required expected delivery in this quarter, before the end of September. DELAY - Delays in cabinet build due to agreement of Sunday working/road closure. Likely completion mid-October
Chapel St Leonards 12 – Shifted in plan. Meeting organised for next week for wayleave
Cranwell 2 - This cab is planned and job has been designated to the engineers to stand. Cabinet stand and completion is forecast for next quarter
Cranwell 5 – Second survey completed, awaiting formal survey return. Delivery forecast for next quarter
Folkingham 3 – Ready for Service - products will be available to order from this cabinet in approx 2 weeks
Gosberton 5 – Overlay required over the bridge, Next quarter delivery
Grantham 16 - SHIFTED - Expected delivery between October and December
Grantham 21– Power position not agreed with WPD. Site meeting next week
Grantham 34 – Chasing new date with power company for works under traffic management - chasing today 04/09/15
Holbeach St Johns 1 - DELAYED - All poles erected at the weekend, waiting remedial civils work likely to be RFS October - November due to size of the PON
Kirton 5 (amalgamated with 13) - Should be RFS early October as big copper job (De-load / Re-load with cab 13)
Knipton 1 - Ready for service - products should be available to order in approx 1 week.
Langrick 1– DELAY linked to new duct over bridge which requires various meeting with Bridge engineers and Contractors. 1KM of duct work to go over a deep dyke. In progress
Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015
Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015
Lincoln 133 - Cab up and powered, needs copper and fibre, but new duct required which could cause further delay
Metheringham 1 Due to be supplied with power 12th October - (Digby, Roughton?)
Metheringham 6 - Cabinet stood in position. With planners to provide route utilising existing fibre 11/09/15 Due to be supplied with power 12th October
Metheringham 12 - only needs fibre providing and the fibre jointers are delaing with this now
Old Leake 6 – Civils issues are ongoing
Normanby By Spital 2 – Ready for service - services can be ordered from this cabinet in approx. 2 weeks.
Sleaford 28 - Will be RFS 2nd October
South Cockerington 1, 2 & 4 - 1 and 4 are ready for service - products can be ordered from these in approx 2 weeks. 2 has overlay works in progress (over poles)
Spalding 50– New point of connection point found; with the engineering team to be programmed with Western power
Spalding 16 & 26– DELAYED - Completion will probably be in November, new duct required
Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December
Spilsby 1- DELAYED - De-load / Re-load and road closure. Next quarter delivery
Swaton 2 & 3 - Next quarter delivery. HA originally rejected location for Swaton 3; we now have agreement on location.
Swinderby 1 - Cable recovery teams working to try to save the need to put in 3km of new duct
Wickenby 2 – Road crossing for power. 22/10/15
Withern 1- Still chasing power wayleaves with NPG 25/09/15 Meeting organised for today to resolve power wayleave issues
Witham on the Hill. Cabinet 1 is ready for service - products should be available to order in approx 2 weeks. Witham 2 still waiting for cabinet to be stood.
To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide
Enter your postcode in the box to find out how the Onlincolnshire campaign is making a difference to your community...
Test the speed of your broadband with the broadband speed checker