Project Update - Week ending 30th October 2015

30th October 2015

Phasing datesPhasing 7

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 Swinderby 5 & 6 - capacity should be added by the 11th November - please be ready to order your new service

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet  1 on the  LANGRICK exchange

 

 

If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

Bainton 4 – Cabinet stood and powered and jointing works to progress


Bardney 6 – Estimated completion mid-November


Bassingham 4 - only requires power now, booked in for 10/11/15


Billinghay 6 - will be enabled this quarter, before the end of December


Birchwood 63- Estimated completion mid-December


Buckminster 7 - Estimated completion mid-November


Burgh on Bain 3 & 4 - Power wayleaves required. Ongoing discussions with landowner 30/10/5 no change


Chapel St Leonards 12 – Wayleave in place - to be programmed into work schedule


Cranwell 2 - Estimated completion mid-December


Cranwell 5 – Estimated for completion before the end of November


Gosberton 5 – Estimated for completion before the end of December


Grantham 16 - SHIFTED - Expected delivery between October and December. Civils work commenced 09/10/2015


Grantham 21– Estimated completion now early December


Grantham 34 – Estimated completion mid-December


Holbeach St Johns 1 - Estimated completion mid-December


Huttoft 1 - Estimated completion mid-December


Huttoft 3 - Fibre needs to be provided - estimated at the beginning of November 30/10/15 - DELAY Estimate completion mid-December


Kirton 5 DELAY - estimated completion before the end of December


Kirton 8 - estimated completion before the end of December


Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015


Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015


Lincoln 133 - New duct to be installed to allow provision of Copper and Fibre. Work commencing late October 30/10/15 Estimate completion by the end of December


Long Sutton 4 - DSLAM needs moving - estimated completion mid-December


Metheringham 1 - Power connection date has had to be changed as a new source has been identified which required a road crossing - estimated for 12/11/15 Ready for service estimated late November


Metheringham 6 - Power connection date has been changed - now estimated for 12/11/15 FURTHER DELAY - estimated completion for the end of November


Metherinham 14 - Digby - Estimated for completion for the end of November


Old Leake 6 – Civils issues are ongoing - expected to be ready for service mid-December


Normanby By Spital 2 – DELAY - cabinet failed commissioning tests. With Huawei to resolve. Huawei at site 26/10/15 Estimate completion mid-December


North Somercotes 3 - Cabinet has been moved to facilitate new development


South Cockerington 2 - overlay works in progress (over poles) Estimated completion mid-December


South Cockerington 3 - Estimated completion mid-December


Spalding 50– Estimated completion mid-December


Spalding 16 & 26– Estimated completion mid-December


Spalding 26– Estimated completion by the end of November


Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December


Spilsby 1- Estimated for completion before the end of November


Spilsby 4 - Just needs power and certification. Working with power company to get dates for this. Estimated for delivery 14/11/15 late November


Swaton 2 & 3 - Highways Authority originally rejected location for Swaton 3; we now have agreement on location. Estimated cab stand date 12/11/15 Swaton 3 expected completion before the end of November


Swinderby 1 - Planner has released fibres BT can use - expected ready for service mid-December


Tetford EO (3) Estimated completion mid-November


Torksey 3 - Estimated completion mid-November


Wickenby 2 – Estimated completion mid-November


Withern 1- Estimated completion late December


Witham on the Hill 2 - Estimated completion late November

 

October process

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide