Project Update - Week ending 30th September 2016

30th September 2016

Contract two phase one

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in time. BT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

Cabinet 2 on the Little Steeping exchange


Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Dowsby 602 - work complete, now in commissioning

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit and there is more planning associated with doing this

Gosberton 5 – Highways Authority now objectingto size of poling vehicle that needs to be deployed to erect new poles; we are looking to hand dig the holes required for the poles; booked in for 21/11

Holbeach St Johns 1 - Moleplough ongoing. Build now to re-commence; ECD end of November

Metheringham 3/2 (Nocton) - Still with commissioners to finalise records

Spalding 16 – Land owner now wants copies of wayleave agreements before allowing work to commence

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide