Phasing datesPhasing 6-7

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible

 

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet 3 on the HEMSWELL exchange

Cabinet 603 on the HONINGTON exchange

 

 

Please note that we can only provide updates on delayed cabinets.

 

If you have any queries please contact us

 

Delayed cabinets


 

Ancaster 4 – Natural England now given Ok to start. Traffic management applied for to start works. 5.4Km of network to cable. 05/06/15 No Change – awaiting traffic management permission. 12/06/15 Cabling has been started and is ongoing 03/07/15 Cabling is ongoing 10/07/15 Cabling ongoing 4K completed 1.5K left 17/07/15 - still ongoing 24/07/15 remaining cabling is progressing slowly alongside traffic management 31/07/15 Cabling ongoing - no change

 

Bainton 4 –Currently with planners, BT will push for early completion 05/06/15 BT are chasing planners for progression 12/06/15 Still with planning team 03/07/15 No change in situation 17/07/15 No change, BT chasing planning for a resolution 24/07/15 No change 31/07/15 Solution agreed and will be progressing as soon as possible

 

Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December 10/07/15 Meeting held again this week Ref New Duct over bridge Oct - Dec still completion period 24/07/15 road closure required for duct over bridge. No change. 31/07/15 No change

 

Billingborough 1 - Cabinet 1 has some planning delays associated and BT are moving to resolve as soon as possible. We will update within the next week or so on progress. 10/07/15 Planning issues are still being dealt with. We are hoping to have timescales for this in the coming weeks 17/07/15 - still awaiting timescales 24/07/15 No change 31/07/15 BT are looking at all means to expedite this cabinet. The surveys have not revealed any physical issues and the cabinet may be stood within the next two weeks but would then require copper and fibre providing to it.

 

Billingborough 5 – currently taking orders but we are aware of issues associated with this cabinet and Billingborough 5 and are trying to remedy these as soon as possible 17/07/15 No change 24/07/15 No change 31/07/15 No change whilst planning for Billingborough 1 progresses

 

Birchwood 38 - 31/07/15 Cabinet is ready for service - products should be available within 2 weeks.

 

Birchwood 63 - DELAYED – this cabinet will not be completed until quarter of October - December 24/07/15 no change. Cabling started but expected completion as per previous.

 

Birchwood 72 - Just needs copper and Light - should be completed before the end of this month. 10/07/15 Cabinet has a land wayleave issue but the entire network is proven. 17/07/15 No change 24/07/15 No change 31/07/15 Wayleave issue still stands but this is being dealt with

 

Bottesford 5 – 31/07/15 Cabinet is ready for service - products should be available within 2 weeks.

 

Buckminster 7 - Road crossing was completed at the weekend and now working on cabling 17/07/15 Sunday required for stand up of cabinet. Expected delivery in this quarter, before the end of September 31/07/15 No change

 

Chapel St Leonards 12 – Shifted in plan. Now expected to be excepting orders in August, 10/07/15 – no change 17/07/15 Wayleave outstanding with developer. 31/07/15 No change

 

Corby Glen 1 & 2 – Traffic management authorisation has caused these to be delayed. Set to be delivered this quarter, before the end of September. 10/07/15 Traffic management issues remain. Trying to rectify 17/07/15 A1+ insist on 3 month notice for blockages either side of A1. Expected delivery this quarter. 24/07/15 No change 31/07/15 A1+ will not allow for blockages to be cleared or access for cabling until the 7th September

 

Cranwell 2 - Delays linked to Ministry of Defence property and survey for Dslam now complete and with planning. 10/07/15 No change 24/07/15 wayleave required for new DSLAM cabinet. Contact made with MOD and discussions are due next week 31/07/15 Wayleave in place - works can now progress

 

Cranwell 5 – No longer shifted to August - this cabinet should be enabled before the end of the month as now only needs fibre connecting to it. 10/07/15 POSSIBLE DELAY The structure may need to be moved. 17/07/15 No change 24/07/15 second survey completed Tuesday. Awaiting formal survey return. 31/07/15 No change

 

Folkingham 1 – this cabinet should be enabled before the end of the month 10/07/15 No change 17/07/15 2 additional blockages to be cleared, cabinet expected to be live mid-August. 24/07/15 No change 31/07/15 Still scheduled for build completion mid-August

 

Folkingham 3 – shifted slightly in plan due to delays. Should be enabled before the end of September

 

Fulbeck 3 – this cabinet should be enabled before the end of the month. Just needs fibre feeding to it. 10/07/15 Still Aiming for end of Month. Cabling and trenching ongoing 17/07/15 no change 23/07/15 fully cabled. Should be RFS by end of month/first week Aug (Services should be available beginning of August) 31/07/15 Still planned to be RFS n the first week of August. Two weeks after this products will be available

 

Gosberton 5 – BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack. 05/06/15 No change 12/06/15 – overlay works have been issued to engineers. 03/07/15 ongoing 10/07/15 Ongoing Will has asked for meeting with highways and Bridge people to try and move it forward work still with Network Rail. 17/07/15 Chasing for meeting to agree way forward.23/07/15 Network Rail engineer on leave. Will chase again next week. 31/07/15 No change

 

Grantham 16 SHIFTED- New duct on Road Crossing requiring a road closure. Engineers are still waiting for dates for when this can be completed. 10/07/15 No Change 17/07/15 SHIFTED - Expected delivery between October and December 2015 24/07/15 No change 31/07/15 No change

 

Grantham 21– Just needs power and Light - completion July 17/07/15 Power wayleave still required - chasing with power company 24/07/15 No change 31/07/15 Power wayleaves still required to provide power

 

Grantham 34 – 500mts power which will delay enablement until July according to Western Power. 12/06/15 No change 03/07/15 works are with Western Power 10/07/15 No Change 17/07/15 chasing new date with power company for works under traffic management 23/07/15 Still awaiting date 31/07/15 Still with power company to supply electric

 

Holbeach St Johns 1 - DELAYED – Will not be complete until July – September

 

Honington 1 – power provision ongoing – long route which has meant delays. 10/07/15 Power connection date 15th Aug 24/07/15 No change 31/07/15 No Change

 

Kirton 5 (amalgamated with 13) - work is with the engineers and is still pending. 05/06/15 No change 12/06/15 Awaiting overlay works for copper cable 03/07/15 ongoing 10/07/15 Still Waiting Duct work to Link these 24/07/15 No change 31/07/15 No change

 

Knipton 1 & 3 – these cabinets should be enabled by the end of the month. 10/07/15 Duct works continuing at present 17/07/15 no change 24/07/15 one DSLAM still to build. Likely delivery now mid-August. 31/07/15 No change

 

Langrick 1– DELAY linked to new duct over bridge which requires various meeting with Bridge engineers and Contractors. 10/07/15 Meeting held this week to try and progress duct over Bridge 17/07/15 Meeting held and awaiting programme data from supplier 24/07/15 No change 31/07/15 No change

 

Langrick 2 – this cabinet should be enabled by the end of the month 24/07/15 No change 31/07/15 Still requires copper and fibre - DELAYED, will not be ready for service before the end of the month

 

Lincoln 76 SHIFTED- this cabinet should be enabled by the end of the month. DELAYED - Now expected late quarter 3, November - December 2015

 

Lincoln 132 SHIFTED – Shifted in the plan - due for deployment July – September 2015DELAYED - Now expected late quarter 3, November - December 2015

 

Lincoln 133 - New duct required between existing cabinet and new cabinet 03/07/15 - ongoing 10/07/15 Waiting for job to come through from planning to deal with copper ties 17/07/15 - delivery expected before the end of September. 24/07/15 No change 31/07/15 Needs copper and fibre feeding to it and should then be ready for service

 

Old Leake 1, 3, 4, 5, 6 – DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages. 10/07/15 Still progressing with blockage clearance. Old Leake 5 will be considerably delayed as a road closure required for this which requires 13 week notice. 17/07/15 Cabinet 1, 3 and 4 expected this quarter, before the end of September. Cabinet 5 requires road closure and 6 has extensive overlay requirements. 24/07/15 No change 31/07/15 All cabinets are in position and are powered and have copper feeding to them. Now just need cabling

 

Normanby By Spital 2 – High cost power - quote approved; with WPD delivery expected before the end of September

 

Sleaford 28 - Looking to use an existing fibre to expedite delivery. This cabinet should be completed by the end of this quarter, before the end of September. 10/07/15 No Change 17/07/15 no change. 24/07/15 No change 31/07/15 This cabinet should be available by the end of September

 

Spalding 50– Shuttering complete. With WPD to resource. End June / early July 10/07/15 No Change 17/07/15 Pushing for power this quarter. 24/07/15 No change 31/07/15 No change

 

Spalding 16 & 26– DELAYED. Should be completed by the end of this quarter, before the end of September 10/07/15 No Change 17/07/2015 no change FURTHER DELAY - Completion will probably be in November

 

Spalding 45 – DELAYED. Will be completed towards the end of this quarter, around September time. 10/07/15 one section of Duct overlay (overhead wiring) required 17/07/15 New position agreed to avoid wayleave - now likely to be delivered between October and December

 

Spilsby 1- only requires copper and fibre feeding to it now. Should be completed soon. 10/07/15 The cabinet may need to be moved - meeting with highways 17/07/15 SHIFTED Now will not be completed October - December as cabinet needs to be rebuilt. 24/07/15 No change

 

Sudbrooke Park 18 – Direct labour engineers on with now, expected delivery 1st week of July 10/07/2015 Cabling delayed on final section linked to TM 24/07/15 No change 31/07/15 This cabinet should be ready to order products from in mid August

 

Swaton 2 & 3 – Due for completion this quarter, before the end of September

 

Whaplode Drove 5 - 24/07/15 ready for service. Should be available to take orders within two weeks. 31/07/15 Should be ready for orders at the end of next week

 

Wickenby 2 – works are currently progressing to feed fibre to new structure. 10/07/15 The cabinet is due to be stood between the 14th and 24th June. All ducting has been proved. 88m of fibre remaining to be jointed. 17/07/15 Expected delivery this quarter, should be able to order services before September 2015 24/07/15 No change 31/07/15 No change

 

Withern 1,3 & 4 - these cabinet should be enabled by the end of the month 10/07/15 Still on target but one cabinet is waiting a duct overlay (overhead wiring) section. No change 24/07/15 No change 31/07/15 Should be completed and available for orders at the end of August

 

Witham on the Hill 1 & 2 31/07/15 cabinet 1 is stood in position with power, just needs copper and fibre feeding to it. Cabinet 2 still needs standing but this is being chased.


 progress july

 

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide