CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in timeBT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

Completed cabinet list

Cabinet V1 on the Baumber exchange

Cabinet 3 on the Culverthorpe exchange

Cabinet 5 on the Scremby 5 exchange

Cabinet 2 on the Swaby exchange

Cabinet 18 on the Washingborough exchange

Cabinet 19 on the Washingborough exchange

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Delayed cabinets

Bourne 32 - Stood in position, coppered, powered and certificated. Final engineering work expected to be complete next week.

Fulbeck 606 - BT intend to move the cabinet so that it provides more benefit, replanning required. BT estimate planning to complete in September.

Gosberton 5 – All new poles and aerial cable erected; Openreach operatives are currently working on this cabinet, final engineering work expected to be complete next week.

Holbeach St Johns 1 - Issue with the duct route; 300m of new duct required, furthe traffic management required, engineering work expected to be completed in early May.

Spalding 16 – Land owner looking at wayleave agreements before work can commence 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide