Project Update - Week ending 3rd July 2015

3rd July 2015

Phasing datesPhasing 6-7

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible

 

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice


Cabinet 5 on the BILLINGBOROUGH exchange

Cabinet 4 on the BILLINGHAY exchange

Cabinet 22 on the BOURNE exchange

Cabinet 1 on the CROWLAND exchange

Cabinet 6 on the CROWLAND exchange

Cabinet 12 on the KIRTON exchange

Cabinet 11 on the LONG SUTTON exchange

Cabinet 5 on the NORTH THORESBY exchange

Cabinet 3 on the PARSON DROVE exchange

Cabinet 9 on the RUSKINGTON exchange

Cabinet 36 on the STAMFORD exchange

Cabinet 1 on the SWATON exchange


 

Please note that we can only provide updates on delayed cabinets.


If you have any queries please contact us

 

 

Delayed cabinets

Ancaster 4 – Natural England now given Ok to start. Traffic management applied for to start works. 5.4Km of network to cable. 05/06/15 No Change – awaiting traffic management permission. 12/06/15 Cabling has been started and is ongoing 03/07/15 Cabling is ongoing


Bainton 4 –Currently with planners, BT will push for early completion 05/06/15 BT are chasing planners for progression 12/06/15 Still with planning team 03/07/15 No change in situation


Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October - December


Billingborough 1 - Cabinet 1 has some planning delays associated and BT are moving to resolve as soon as possible. We will update within the next week or so on progress


Birchwood 38 - New duct laid and blown fibre tubing provided. Cab stand with contractor. Will urge for completion early July


Birchwood 63 - DELAYED – this cabinet will not be completed until quarter of October - December


Birchwood 72 - Just needs copper and Light - should be completed before the end of this month


Bottesford 5 – Should be completed by the end of the month. Just needs fibre linking up to it

Buckminster 7 - Road crossing was completed at the weekend and now working on cabling    


Chapel St Leonards 12 – Shifted in plan. Now expected to be excepting orders in August


Corby Glen 1 & 2 – Traffic management authorisation has caused these to be delayed. Set to be delivered this quarter, before the end of September    


Cranwell 2 - Delays linked to Ministry of Defence property and survey for Dslam now complete and with planning


Cranwell 5 – No longer shifted to August -  this cabinet should be enabled before the end of the month as now only needs fibre connecting to it


Folkingham 1 – this cabinet should be enabled before the end of the month


Folkingham 3 – shifted slightly in plan due to delays. Should be enabled before the end of September


Fulbeck 3 – this cabinet should be enabled before the end of the month. Just needs fibre feeding to it.


Gosberton 5 – BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack. 05/06/15 No change 12/06/2015 – overlay works have been issued to engineers. 03/07/2015 ongoing


Grantham 16 - New duct on Road Crossing requiring a road closure. Engineers are still waiting for dates for when this can be completed.   


Grantham 21 – Just needs power and Light - completion July


Grantham 34 – 500mts power which will delay enablement until July according to Western Power. 12/06/15 No change 03/07/15 works are with Western Power


Holbeach St Johns 1 - DELAYED – Will not be complete until July – September


Honington 1 – power provision ongoing – long route which has meant delays.


Honington 603 – this cabinet should be enabled by the end of the month. Currently awaiting power connection and certification.


Horsington R1 – Ready for Service. Should be accepting orders in the coming weeks.


Kirton 5 (amalgamated with 13) - work is with the engineers and is still pending. 05/06/15 No change 12/06/15 Awaiting overlay works for copper cable 03/07/15 ongoing


Knipton 1 & 3 – these cabinets should be enabled by the end of the month


Langrick 1 – DELAY linked to new duct over bridge which requires various meeting with Bridge engineers and Contractors.


Langrick 2 – this cabinet should be enabled by the end of the month


Lincoln 76 - this cabinet should be enabled by the end of the month


Lincoln 132 – Shifted in the plan - due for deployment July – September 2015


Lincoln 133 - New duct required DSLAM to PCP 03/07/15 - ongoing


Old Leake 1, 3, 4, 5, 6 – DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages


Normanby By Spital 2 – High cost power - quote approved; with WPD


Risegate 3 – should be ready to take orders in the coming weeks. This cabinet is ‘ready for service.’ Waiting for computer systems to be updated.


Sleaford 28 - Looking to use an existing fibre to expedite delivery. This cabinet should be completed by the end of this quarter, before the end of September.


Spalding 50 – Shuttering complete. With WPD to resource. End june / early July


Spalding 16 & 26 – DELAYED. Should be completed by the end of this quarter, before the end of September


Spalding 45 – DELAYED. Will be completed towards the end of this quarter, around September time.

    
Spilsby 1- only requires copper and fibre feeding to it now. Should be completed soon.


Spilsby 9 - This cabinet is now complete from an engineering perspective; services will be available within the next 2 weeks


Sudbrooke Park 18 – Direct labour engineers on with now, expected delievery 1st week of July


Wickenby 2 – works are currently progressing to feed fibre to new structure. A change in the plan for this has caused delays. Apologies, but the majority of those connected should benefit in the long term.


Withern 1,3 & 4 - these cabinet should be enabled by the end of the month



progress july

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide